5500 W 98TH ST 90045
Certificate Information: 5500 W 98TH ST 90045
- Application / Permit
- 22016-10000-23411
- Plan Check / Job No.
- B22LA15490
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- **ePlan**LAX CONRAC** LEVEL 1 - READY/RETURN AND IDLE STORAGE OPERATIONS 143,959 SF PAVEMENT MARKINGS FOR READY CAR STAGING (198 SPACES) AND IDLE STORAGE (110 STORAGE STALLS) CUSTOMER ENTRANCE AND EXIT PLAZAS, INCLUDING PARKING CONTROL EQUIPMENT JOCKEY ENTRANCE AND EXITS, INCLUDING PARKING CONTROL EQUIPMENT INTERIOR FIT-OUT OF EMPLOYEE OFFICES AND BREAK ROOM IN BASE BUILDING SHELL SPACE (1,561 SF) LEVEL 5 - CUSTOMER SERVICE BUILDING NTERIOR T.I. OF CUSTOMER LOBBY (1,252 SF) INTERIOR T.I. OF EMPLOYEE OFFICES & BREAK ROOM (548 SF)
- Permit Issued
- Issued on 1/3/2024
- Issuing Office
- Current Status
- Issued on 1/3/2024
Permit Application Status History
| Submitted | 8/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | GARO TELMI |
| Corrections Issued | 9/8/2022 | DEAN RYAN REYES |
| Quality Review Completed | 9/8/2022 | LIPING TENG |
| Applicant returned to address corrections | 7/13/2023 | GARO TELMI |
| Applicant returned to address corrections | 8/5/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/5/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/17/2023 | GARO TELMI |
| Plan Check Approved | 12/21/2023 | GARO TELMI |
| Issued | 1/3/2024 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 12/1/2022 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 3/1/2023 | Lily Teng |
| Project Permit | Cleared | 3/10/2023 | DEAN RYAN REYES |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2023 | MARYAM AZARBAYJANI |
| Sewer availability | Cleared | 6/13/2023 | MARYAM AZARBAYJANI |
| Airport buildings | Cleared | 6/16/2023 | ANDREW KO |
| City owned building/parcel | Cleared | 11/3/2023 | DEAN RYAN REYES |
Contact Information
| Architect | Gerber,, Jeffrey P; Lic. No.: C27945 | 14 ESTANCIA PLACE THE WOODLANDS, TX 77309 |
| Contractor | Buildrite Construction Corp; Lic. No.: 976028-B | 600 CHASTAIN RD NW STE 326 KENNESAW, GA 30144 |
| Engineer | Faghihi,, Mahmoud; Lic. No.: S5789 | 888 S FIGUEROA ST 18TH FLOOR LOS ANGELES, CA 90017 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Fireproofing | 4/8/2024 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 7/22/2024 | Partial Approval | ALAN NOVAK |
| Insulation | 8/21/2024 | Approved | ALAN NOVAK |
| Light Gage Steel Frame | 8/22/2024 | Approved | ALAN NOVAK |
| Drywall Nailing | 8/23/2024 | Partial Approval | ALAN NOVAK |
| Drywall Nailing | 8/26/2024 | Approved | ALAN NOVAK |
| Insulation | 8/27/2024 | Approved | ALAN NOVAK |
| Drywall Nailing | 9/5/2024 | Partial Approval | ALAN NOVAK |
| Wood Frame | 10/2/2024 | Approved | ALAN NOVAK |
| Insulation | 10/11/2024 | Partial Approval | ALAN NOVAK |
| Pre-Inspection | 10/28/2024 | Approved | ALAN NOVAK |
| Partition/T-Bar Ceiling | 3/13/2025 | Partial Approval | ALAN NOVAK |
| Wall Anchors | 3/14/2025 | Approved | ALAN NOVAK |
| Final | 5/19/2025 | Not Ready for Inspection | NICK LAROCCA |
| Green Building Final | 5/19/2025 | Approved | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | NICK LAROCCA |
| Smoke Detectors | 5/19/2025 | Approved | NICK LAROCCA |
| Final | 1/29/2026 | Not Ready for Inspection | NICK LAROCCA |