2013 N VESTAL AVE 90026
Certificate Information: 2013 N VESTAL AVE 90026
- Application / Permit
- 22016-10000-23347
- Plan Check / Job No.
- B22LA15424
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- MANDATORY SOFT-STORY SEISMIC RETROFIT AS PER LABC CH 93. INSTALL GRADE BEAM USING SPECIAL CANTILEVER COLUMN SYSTEM.
- Permit Issued
- Issued on 11/16/2022
- Issuing Office
- Current Status
- CofC Issued on 4/21/2023
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | VARAND SARKISIAN |
| Corrections Issued | 9/6/2022 | VARAND SARKISIAN |
| Quality Review Completed | 9/7/2022 | HANS SANTIAGO |
| Building Plans Picked Up | 9/9/2022 | APPLICANT |
| Plan Check Approved | 9/21/2022 | VARAND SARKISIAN |
| Issued | 11/16/2022 | APPLICANT |
| OK for CofC | 4/20/2023 | VAHE KELEDJIAN |
| CofC Issued | 4/21/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/15/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 894 SANTA MARIA CIRCLE DUARTE, CA 91010 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/14/2022 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Steel/Welding | 12/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 12/20/2022 | Conditional Approval | VAHE KELEDJIAN |
| Excavation/Setback/Form/Re-Bar | 12/20/2022 | Conditional Approval | VAHE KELEDJIAN |
| Structural Steel Frame | 12/20/2022 | Partial Approval | VAHE KELEDJIAN |
| Wood Frame | 12/28/2022 | Approved | VAHE KELEDJIAN |
| Insulation | 1/18/2023 | Approved | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 2/1/2023 | Approved | JAIME RIOS |
| Final | 2/16/2023 | Partial Inspection | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 2/16/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Final | 2/21/2023 | Corrections Issued | VAHE KELEDJIAN |
| Smoke Detectors | 2/21/2023 | Approved | VAHE KELEDJIAN |
| Final | 4/20/2023 | OK for CofC | VAHE KELEDJIAN |