3516 S GRAND VIEW BLVD 90066

Certificate Information: 3516 S GRAND VIEW BLVD 90066

Application / Permit
22016-10000-23137
Plan Check / Job No.
B22LA15287
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
****ePlan**** Remodel (e) 2-story SFD to add an elevator, re-arrange stairs to the roof deck, change interior layout, reconfigure roof and floor decks
Permit Issued
Issued on 4/24/2023
Issuing Office
Current Status
Issued on 4/24/2023

Permit Application Status History

Submitted 8/3/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 REZA HAGHIGHAT
Corrections Issued 8/30/2022 REZA HAGHIGHAT
Quality Review Completed 9/13/2022 CHIHARU SUZUKI
Applicant returned to address corrections 2/15/2023 REZA HAGHIGHAT
Plan Check Approved 3/4/2023 REZA HAGHIGHAT
Issued 4/24/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/18/2022 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 10/19/2022 DINAH GARIN
Sewer availability Cleared 10/19/2022 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 10/20/2022 VASIL MIHALEV
ZA Case Cleared 10/26/2022 RYAN LY

Contact Information

Contractor Farnsworth W Builders; Lic. No.: 947797-B       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423
Engineer Andrejic,, Milos; Lic. No.: NA67443       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/12/2023 Partial Approval JESUS PINEDA
Deputy Drilled-In Anchors 10/23/2023 Conditional Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 10/23/2023 Not Ready for Inspection JESUS PINEDA
Excavation/Setback/Form/Re-Bar 10/27/2023 Corrections Issued CLAYTON GRAHAM
Deputy Drilled-In Anchors 10/31/2023 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 11/1/2023 Approved JESUS PINEDA
Special/Order Compliance 11/1/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Partial Approval JESUS PINEDA
PLUMBING-Rough 11/15/2023 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Partial Approval JESUS PINEDA
Drywall Nailing 4/30/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 4/30/2024 Corrections Issued TEMISTOCLES CAAL
Drywall Nailing 5/1/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 5/1/2024 Approved JESUS PINEDA
Deputy Steel/Welding 5/23/2024 Conditional Approval JESUS PINEDA
Rough-Elec/Plmb/HVAC 11/15/2024 Not Ready for Inspection DANIEL VERA
Shower Pan 11/15/2024 Approved DANIEL VERA
ELECTRICAL-Rough 11/26/2024 Approved DANIEL VERA
HVAC-Rough 11/26/2024 Approved DANIEL VERA
Deputy Wood Construction 12/18/2024 Conditional Approval DANIEL VERA
BUILDING-Rough-Frame 12/19/2024 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 12/24/2024 Approved DANIEL VERA
Final 12/24/2024 Corrections Issued DANIEL VERA
Interior/Exterior Lathing 12/24/2024 Partial Approval DANIEL VERA
Insulation 1/30/2025 Approved EVAN COOPER
Drywall Nailing 2/18/2025 Approved DANIEL VERA
Interior/Exterior Lathing 2/25/2025 Approved DANIEL VERA
Pre-Inspection 6/24/2026 Partial Inspection ARAM AVEDISIAN