1622-1624 W SUNSET BLVD 90026
Certificate Information: 1622-1624 W SUNSET BLVD 90026
- Application / Permit
- 22016-10000-23020
- Plan Check / Job No.
- B22LA15212
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Gymnasium
- Work Description
- TENANT IMPROVEMENT FOR CHANGE OF USE FROM GROCERY STORE INTO A CLIMBING GYM. See Comment.
- Permit Issued
- Issued on 5/11/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | TSE MING HUANG |
| Corrections Issued | 9/1/2022 | TSE MING HUANG |
| Quality Review Completed | 9/6/2022 | KEN GILL |
| Building Plans Picked Up | 9/9/2022 | APPLICANT |
| Applicant returned to address corrections | 9/23/2022 | TSE MING HUANG |
| Disabled Access Plans Picked Up | 9/29/2022 | APPLICANT |
| Applicant returned to address corrections | 11/2/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 11/23/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 12/6/2022 | TSE MING HUANG |
| Plan Check Approved | 5/10/2023 | TSE MING HUANG |
| Issued | 5/11/2023 | APPLICANT |
| CofO in Progress | 11/29/2023 | KATY RAMIREZ |
| CofO Issued | 11/30/2023 | ERNESTO CORRAL |
| Permit Finaled | 11/30/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/8/2022 | LOUIS ORTEGA |
| CPC | Cleared | 9/8/2022 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2022 | CELINA MORENO |
| Sewer availability | Cleared | 9/15/2022 | CELINA MORENO |
| ZA Case | Cleared | 10/3/2022 | RYAN LY |
| Green Code | Cleared | 10/27/2022 | AARON COSTA |
| Supp. Use District POD/CDO/TDO | Cleared | 10/27/2022 | ERICK MORALES |
| ZI | Cleared | 10/27/2022 | ERICK MORALES |
| DAS Clearance | Cleared | 11/18/2022 | TSE MING HUANG |
| Encroachment in public way | Cleared | 3/2/2023 | ANTHONY TRAN |
Contact Information
| Architect | Ziese,, Daniel J; Lic. No.: C32234 | 612 MOULTON AVENUE UNIT 7 LOS ANGELES, CA 90031 |
| Contractor | Zeledon Design And Development; Lic. No.: 554524-B | 114 E MISSION ROAD FALLBROOK, CA 92028 |
| Engineer | Ashley,, Charles R; Lic. No.: S5258 | 1229 CARMEL ST SAN LUIS OBISPO, CA 93401 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/20/2023 | Approved | RAFAEL CORTES |
| Wood Frame | 8/29/2023 | Partial Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 9/6/2023 | Approved | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 9/15/2023 | Partial Approval | RAFAEL CORTES |
| Final | 11/9/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 11/9/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 11/9/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 11/22/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Reinforced Masonry Frame | 11/22/2023 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 11/22/2023 | Approved | KATY RAMIREZ |
| Final | 11/28/2023 | Partial Inspection | KATY RAMIREZ |
| Special/Order Compliance | 11/28/2023 | Approved | ALFREDO LOPEZ |
| Final | 11/29/2023 | OK to Issue CofO | KATY RAMIREZ |
| Reinforced Masonry Frame | 11/29/2023 | Approved | KATY RAMIREZ |