189 S THE GROVE DR D1 90036
Certificate Information: 189 S THE GROVE DR D1 90036
- Application / Permit
- 22016-10000-22946
- Plan Check / Job No.
- B22LA15125
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Interior and exterior tenant improvement, change of use from restaurant to retail with trellis addition to replace existing
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Current Status
- CofO Issued on 5/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 9/13/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 9/15/2022 | PETER KIM |
| Applicant returned to address corrections | 12/7/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/27/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/1/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 3/1/2023 | ARMEN JIVALAGIAN |
| Plan Check Approved | 3/15/2023 | ARMEN JIVALAGIAN |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 5/22/2024 | JACOB MYERS |
| Permit Finaled | 5/24/2024 | ERNESTO CORRAL |
| CofO Issued | 5/24/2024 | ERNESTO CORRAL |
| Permit Finaled | 5/24/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/29/2022 | STEVE MELGAR |
| "D" conditions | Cleared | 10/7/2022 | MARITZA PRZEKOP |
| "Q" conditions | Cleared | 10/7/2022 | MARITZA PRZEKOP |
| "T" removal | Cleared | 10/7/2022 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 10/7/2022 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 10/7/2022 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 10/7/2022 | MARITZA PRZEKOP |
| ZA Case | Cleared | 10/7/2022 | MARITZA PRZEKOP |
| ZI | Cleared | 10/7/2022 | MARITZA PRZEKOP |
| Sewer availability | Cleared | 10/12/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2022 | STEVE MELGAR |
| Green Code | Cleared | 10/20/2022 | AARON COSTA |
| DAS Clearance | Cleared | 10/25/2022 | Hernan Arreola |
| Hydrant and Access approval | Cleared | 11/4/2022 | GILBERT URREA |
| Address approval | Cleared | 12/15/2022 | AMAAN MALIK |
| Highway dedication | Cleared | 1/6/2023 | STEVE MELGAR |
| Abandoned oil well | Cleared | 1/8/2023 | GILBERT URREA |
Contact Information
| Architect | Elton,, Lisa T; Lic. No.: NA36983 | , |
| Contractor | M C Construction Management Inc; Lic. No.: 526931-B | , |
| Engineer | Gallagher,, Chris J; Lic. No.: C83624 | 8227 BRECKSVILLE RD BRECKSVILLE, OH 44141 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2023 | Partial Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 5/25/2023 | Partial Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 5/31/2023 | Partial Approval | JEROME BLACKWOOD |
| Green Building Rough | 5/31/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 5/31/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Rough | 5/31/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 5/31/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Fireproofing | 6/1/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 6/1/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 6/1/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Fireproofing | 6/5/2023 | No Access for Inspection | JEROME BLACKWOOD |
| Deputy Methane Barrier | 6/5/2023 | No Access for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 6/5/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 6/5/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Fireproofing | 6/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Methane Barrier | 6/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 6/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 6/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 6/15/2023 | Partial Approval | ALFREDO LOPEZ |
| Green Building Rough | 6/15/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 6/15/2023 | Partial Inspection | ALFREDO LOPEZ |
| METHANE-Rough | 6/15/2023 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 6/15/2023 | Partial Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 6/20/2023 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 6/20/2023 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 6/27/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 6/29/2023 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 7/3/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 7/11/2023 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 7/21/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Structural Steel Frame | 7/21/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Light Gage Steel Frame | 7/25/2023 | Partial Inspection | ALFREDO LOPEZ |
| Structural Steel Frame | 7/25/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Drilled-In Anchors | 8/3/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/3/2023 | Partial Approval | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 8/3/2023 | Partial Approval | GREGORY POMISH |
| Insulation | 8/3/2023 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 8/4/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/9/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/9/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/11/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Insulation | 8/11/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/11/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/16/2023 | Partial Approval | VAHE KELEDJIAN |
| Insulation | 8/16/2023 | Partial Inspection | VAHE KELEDJIAN |
| Light Gage Steel Frame | 8/25/2023 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 8/30/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 9/7/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 9/13/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Drywall Nailing | 9/15/2023 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 9/21/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 9/21/2023 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 10/3/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/13/2023 | Partial Approval | JACOB MYERS |
| Insulation | 10/13/2023 | Partial Approval | JACOB MYERS |
| Drywall Nailing | 10/17/2023 | Partial Approval | JACOB MYERS |
| Drywall Nailing | 10/25/2023 | Partial Approval | JACOB MYERS |
| Light Gage Steel Frame | 10/25/2023 | Partial Approval | JACOB MYERS |
| Drywall Nailing | 11/1/2023 | Partial Inspection | JACOB MYERS |
| Interior/Exterior Lathing | 11/1/2023 | Partial Approval | JACOB MYERS |
| Deputy Fireproofing | 11/3/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Fireproofing | 11/6/2023 | Conditional Approval | RICARDO ROBLES |
| T-Bar Ceiling | 11/6/2023 | Partial Approval | RICARDO ROBLES |
| Deputy Fireproofing | 11/7/2023 | Partial Approval | JACOB MYERS |
| Deputy Fireproofing | 11/8/2023 | Conditional Approval | RICARDO ROBLES |
| Deputy Fireproofing | 11/9/2023 | Conditional Approval | RICARDO ROBLES |
| Drywall Nailing | 11/13/2023 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 11/17/2023 | Partial Inspection | JACOB MYERS |
| Interior/Exterior Lathing | 11/27/2023 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 12/5/2023 | Not Ready for Inspection | JACOB MYERS |
| Interior/Exterior Lathing | 12/6/2023 | Approved | JACOB MYERS |
| Interior/Exterior Lathing | 12/15/2023 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 12/15/2023 | Partial Approval | RICARDO ROBLES |
| Pre-Inspection | 1/19/2024 | Partial Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 1/31/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 2/6/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 2/26/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 2/28/2024 | Partial Approval | MARTIN TAVITIAN |
| Drywall Nailing | 3/5/2024 | Partial Approval | JACOB MYERS |
| Green Building Rough | 3/7/2024 | Not Ready for Inspection | JACOB MYERS |
| METHANE-Rough | 3/7/2024 | Not Ready for Inspection | JACOB MYERS |
| Wood Frame | 3/7/2024 | Partial Approval | JACOB MYERS |
| Pre-Inspection | 4/11/2024 | Partial Approval | JACOB MYERS |
| Pre-Inspection | 4/12/2024 | Partial Approval | JACOB MYERS |
| Special/Order Compliance | 4/17/2024 | Partial Approval | JACOB MYERS |
| Grading Pre-Inspection | 4/22/2024 | Approved | JACOB MYERS |
| Final | 4/26/2024 | Partial Inspection | JACOB MYERS |
| Green Building Final | 4/26/2024 | Conditional Approval | JACOB MYERS |
| Green Building Rough | 4/26/2024 | Conditional Approval | JACOB MYERS |
| METHANE-Final | 4/26/2024 | Approved | JACOB MYERS |
| METHANE-Rough | 4/26/2024 | Approved | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 4/26/2024 | Approved | JACOB MYERS |
| Wood Frame | 4/26/2024 | Conditional Approval | JACOB MYERS |
| Final | 4/30/2024 | Not Ready for Inspection | JACOB MYERS |
| Green Building Final | 4/30/2024 | Not Ready for Inspection | JACOB MYERS |
| Green Building Rough | 4/30/2024 | Not Ready for Inspection | JACOB MYERS |
| Wood Frame | 4/30/2024 | Partial Approval | JACOB MYERS |
| Final | 5/3/2024 | OK for TCO | JACOB MYERS |
| Green Building Final | 5/3/2024 | Approved | JACOB MYERS |
| Green Building Rough | 5/3/2024 | Approved | JACOB MYERS |
| Wood Frame | 5/3/2024 | Approved | JACOB MYERS |
| Final | 5/8/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 5/14/2024 | Conditional Approval | JACOB MYERS |
| Final | 5/22/2024 | OK to Issue CofO | JACOB MYERS |