1741 W 79TH ST 90047

Certificate Information: 1741 W 79TH ST 90047

Application / Permit
22016-10000-22762
Plan Check / Job No.
B22LA15033
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT PORTION OF (E) DETACHED GARAGE WITH (E) ATTACHED RECREATION ROOM TO ADU PER ORDIANCE AND CONVERT PORTION OF (E) GARAGE TO STORAGE ROOM. ALL WORK PER WFPP
Permit Issued
Issued on 3/29/2023
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2022 APPLICANT
Assigned to Plan Check Engineer 8/10/2022 ALFRED RAMIREZ
Corrections Issued 8/11/2022 ALFRED RAMIREZ
Applicant returned to address corrections 10/13/2022 ALFRED RAMIREZ
Applicant returned to address corrections 11/18/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 11/22/2022 MOHAMMAD ESMAILI
Plan Check Approved 12/2/2022 FARSHAD ALIMOHAMADI
Issued 3/29/2023 APPLICANT
CofO in Progress 1/8/2024 ENRIQUE MIRELES
CofO in Progress 1/8/2024 ENRIQUE MIRELES
CofO Issued 1/10/2024 DEROLD HAUFF
Permit Finaled 1/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/24/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/24/2022 JEANETTE VONG
Sewer availability Cleared 9/24/2022 JEANETTE VONG
Construction within easement Cleared 11/18/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/12/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 7/25/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Approved ENRIQUE MIRELES
Insulation 8/29/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/29/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Approved ENRIQUE MIRELES
Drywall Nailing 10/12/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 10/12/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/11/2023 Approved ENRIQUE MIRELES
Final 12/11/2023 Corrections Issued ENRIQUE MIRELES
Service/Power Release 12/11/2023 Approved ENRIQUE MIRELES
Smoke Detectors 12/11/2023 Approved ENRIQUE MIRELES
Final 12/14/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 12/14/2023 Approved ENRIQUE MIRELES