1241-1243 S MEADOWBROOK AVE 90019
Certificate Information: 1241-1243 S MEADOWBROOK AVE 90019
- Application / Permit
- 22016-10000-22721
- Plan Check / Job No.
- B22LA15003
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EXTERIOR AND INTERIOR REMODEL TO EXISTING 2 STORY DUPLEX BUILDING INCLUDING NEW REAR BALCONY WITH POSTS PER ENGINEER DESIGN.
- Permit Issued
- Issued on 11/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | AUNG SOE |
| Corrections Issued | 8/9/2022 | AUNG SOE |
| Applicant returned to address corrections | 9/7/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 9/30/2022 | ADAM HEGAZI |
| Plan Check Approved | 11/22/2022 | JOSEPH RAFOLS |
| Issued | 11/28/2022 | APPLICANT |
| CofO in Progress | 6/26/2024 | RICHARD DOCKUS |
| CofO Issued | 6/26/2024 | DEROLD HAUFF |
| Permit Finaled | 6/26/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 9/20/2022 | JEANETTE VONG |
| Tenant Habitability Plan | Cleared | 9/20/2022 | ISMAEL HERNANDEZ |
| CPC | Cleared | 11/17/2022 | AMANDA KAINER |
| HPOZ | Cleared | 11/17/2022 | AMANDA KAINER |
Contact Information
| Contractor | Gold Pacific Construction Inc; Lic. No.: 1024672-B | 1134 W 68TH ST LOS ANGELES, CA 90044 |
| Engineer | Tamu,, O C; Lic. No.: C29787 | P O BOX 17083 LONG BEACH, CA 90807 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/2/2022 | Approved | RICHARD DOCKUS |
| METHANE-Barrier | 12/2/2022 | Approved | RICHARD DOCKUS |
| METHANE-Subgrade | 12/2/2022 | Approved | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 12/8/2022 | Conditional Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 12/22/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 12/22/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 12/22/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/3/2023 | Corrections Issued | RICHARD DOCKUS |
| Green Building Rough | 1/3/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| METHANE-Rough | 1/3/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 1/3/2023 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/5/2023 | Approved | RICHARD DOCKUS |
| Green Building Rough | 1/5/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 1/5/2023 | Approved | RICHARD DOCKUS |
| Insulation | 1/20/2023 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 1/27/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 5/25/2023 | Partial Approval | STUART CHAPMAN |
| Shower Pan | 7/20/2023 | Approved | LILIANA PORTILLO |
| Final | 3/14/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Final | 3/14/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 3/14/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 3/22/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Final | 3/22/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 3/22/2024 | Approved | RONNIE MINDANAO |
| Final | 4/16/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 4/16/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Final | 5/15/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 5/15/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Final | 5/21/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Approved | RONNIE MINDANAO |
| Final | 6/4/2024 | Conditional Approval | RONNIE MINDANAO |
| Final | 6/21/2024 | OK to Issue CofO | RICHARD DOCKUS |