140 N ARDMORE AVE 90004
Certificate Information: 140 N ARDMORE AVE 90004
- Application / Permit
- 22016-10000-22718
- Plan Check / Job No.
- B22LA15001
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert Existing 37'2" x 24'10" Garage/Storage to ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/22/2022
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2022 | HANS SANTIAGO |
| Corrections Issued | 8/7/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 8/18/2022 | HANS SANTIAGO |
| Plan Check Approved | 9/14/2022 | ANDREW SANTIAGO |
| Plan Check Approved | 9/22/2022 | ANDREW SANTIAGO |
| No Progress | 9/22/2022 | ANDREW SANTIAGO |
| Plan Check Approved | 9/22/2022 | ANDREW SANTIAGO |
| No Progress | 9/22/2022 | ANDREW SANTIAGO |
| Plan Check Approved | 9/22/2022 | ANDREW SANTIAGO |
| Issued | 9/22/2022 | APPLICANT |
| CofO in Progress | 3/8/2023 | JEFFREY MEAD |
| Permit Finaled | 3/15/2023 | DEROLD HAUFF |
| Permit Finaled | 3/15/2023 | DEROLD HAUFF |
| CofO Issued | 3/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2022 | JEANIE LAM |
| Sewer availability | Cleared | 8/10/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/2/2022 | RUEL COLE |
Contact Information
| Contractor | Green Living Remodeling Corp; Lic. No.: 617148-B | , |
| Contractor | Treeium Inc; Lic. No.: 617148-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/29/2022 | Approved | JEFFREY MEAD |
| Pre-Inspection | 11/7/2022 | Corrections Issued | JEFFREY MEAD |
| Pre-Inspection | 11/16/2022 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/12/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/9/2023 | Not Ready for Inspection | JULIAN AMAYA |
| HVAC-Rough | 1/9/2023 | Approved | JULIAN AMAYA |
| PLUMBING-Rough | 1/9/2023 | Approved | JULIAN AMAYA |
| BUILDING-Rough-Frame | 1/11/2023 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/11/2023 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 1/11/2023 | Approved | JEFFREY MEAD |
| Insulation | 1/13/2023 | Partial Approval | JEFFREY MEAD |
| Insulation | 1/18/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 1/18/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 1/23/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/17/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/17/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/23/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 2/23/2023 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 2/23/2023 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/23/2023 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 2/23/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/1/2023 | Approved | JEFFREY MEAD |
| Final | 3/1/2023 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 3/1/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 3/1/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/1/2023 | SGSOV Approved | JEFFREY MEAD |
| Final | 3/3/2023 | OK to Issue CofO | JEFFREY MEAD |