3729 S MAY ST 90066

Certificate Information: 3729 S MAY ST 90066

Application / Permit
22016-10000-22649
Plan Check / Job No.
B22LA14941
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED GARAGE CONVERSION TO ADU
Permit Issued
Issued on 10/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2022 APPLICANT
Assigned to Plan Check Engineer 8/1/2022 SAMUEL GONZALEZ
Corrections Issued 8/1/2022 SAMUEL GONZALEZ
Building Plans Picked Up 8/5/2022 APPLICANT
Issued 10/14/2022 APPLICANT
CofO in Progress 10/3/2023 RICHARD STEINBACH
Permit Finaled 10/7/2023 DANIEL ORRANTE
CofO Issued 10/7/2023 DANIEL ORRANTE
Permit Finaled 10/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/11/2022 CATHERINE ADROVER
Sewer availability Cleared 8/11/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 9/8/2022 CATHERINE ADROVER

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/15/2022 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 12/5/2022 Corrections Issued JESUS RODRIGUEZ
Deputy Steel/Welding 12/14/2022 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/5/2023 Partial Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 1/31/2023 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 1/31/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 1/31/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 2/27/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Approved JESUS RODRIGUEZ
Green Building Rough 2/27/2023 Approved JESUS RODRIGUEZ
Insulation 2/27/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/27/2023 Approved JESUS RODRIGUEZ
Shower Pan 2/27/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 3/1/2023 Approved JOHN KIDWELL
HVAC-Final 8/17/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/17/2023 Corrections Issued HERBERT GIRON
Smoke Detectors 8/17/2023 Approved HERBERT GIRON
Final 9/26/2023 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/29/2023 Approved JESUS RODRIGUEZ
Final 9/29/2023 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 9/29/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 9/29/2023 Approved JESUS RODRIGUEZ