600 WORLD WAY 90045
Certificate Information: 600 WORLD WAY 90045
- Application / Permit
- 22016-10000-22558
- Plan Check / Job No.
- B22LA14849
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- **ePlan**LAX Project** Tenant Improvement consisting of the installation of equipment racks and radios installed inside existing rooms throughout the terminal. Associated cable ladders, equipment backboards, and conduit routing supported by the structure are also included in the scope of work.
- Permit Issued
- Issued on 6/20/2023
- Issuing Office
- Current Status
- Issued on 6/20/2023
Permit Application Status History
| Submitted | 7/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | EDUARDO RODRIGUEZ |
| Corrections Issued | 8/17/2022 | EDUARDO RODRIGUEZ |
| Quality Review Completed | 8/18/2022 | LIPING TENG |
| Applicant returned to address corrections | 12/12/2022 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 2/2/2023 | EDUARDO RODRIGUEZ |
| Issued | 6/20/2023 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 8/9/2022 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 8/20/2022 | Lily Teng |
| Plan Approval | Cleared | 8/26/2022 | KATHERINE RICE |
| Airport buildings | Cleared | 8/29/2022 | ANDREW KO |
| Project Permit | Cleared | 11/16/2022 | EDUARDO RODRIGUEZ |
| City owned building/parcel | Cleared | 11/18/2022 | EDUARDO RODRIGUEZ |
Contact Information
| Contractor | Aztecs Telecom Inc; Lic. No.: 890747-B | , |
| Engineer | Teng,, Albert Rhui-Hong; Lic. No.: C41170 | 2362 MCGAW AVE IRVINE, CA 92614 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/29/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 2/6/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 3/13/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 3/14/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 4/26/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 6/4/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 7/25/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 8/23/2024 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 8/23/2024 | Approved | ALAN NOVAK |
| Deputy Drilled-In Anchors | 9/26/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 10/4/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 4/28/2025 | Approved | NICK LAROCCA |
| Deputy Fireproofing | 5/8/2025 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 5/23/2025 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 6/16/2025 | Approved | NICK LAROCCA |