3730 W SENECA AVE 90039

Certificate Information: 3730 W SENECA AVE 90039

Application / Permit
22016-10000-22478
Plan Check / Job No.
B22LA14785
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*eplan* CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/7/2023
Issuing Office
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2022 APPLICANT
Assigned to Plan Check Engineer 8/3/2022 SELLA BENYAMIN
Corrections Issued 8/3/2022 SELLA BENYAMIN
Plan Check Approved 9/14/2022 SELLA BENYAMIN
Issued 2/7/2023 APPLICANT
CofO in Progress 11/18/2025 NICHOLAS LOPEZ
Permit Finaled 11/19/2025 DEROLD HAUFF
Permit Finaled 11/19/2025 DEROLD HAUFF
CofO Issued 11/19/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/10/2022 TREVOR QUAN
Sewer availability Cleared 8/10/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/12/2022 TREVOR QUAN

Contact Information

Architect Jackowski,, Holli Lynn; Lic. No.: NA38533       ,
Contractor M R D Construction; Lic. No.: 960463-B       ,
Engineer Wu,, Allen Chun-Ying; Lic. No.: NA69385       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/24/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 4/11/2023 Partial Approval STUART CHAPMAN
Sewer 4/11/2023 Approved STUART CHAPMAN
Underground Mechanical 4/11/2023 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 4/20/2023 Approved SCOTT FINNILA
ELECTRICAL-Rough 6/12/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 6/12/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/29/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 8/30/2023 Partial Approval JOSH MEISTER
Deputy Drilled-In Anchors 9/20/2023 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Corrections Issued HAMIK HARTOUNIAN
Insulation 10/4/2023 Not Ready for Inspection JOSH MEISTER
Interior/Exterior Lathing 10/4/2023 Approved JOSH MEISTER
ELECTRICAL-Rough 10/10/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 10/10/2023 Corrections Issued HAMIK HARTOUNIAN
Shower Pan 10/30/2023 Conditional Approval HAMIK HARTOUNIAN
Wood Frame 10/30/2023 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 11/3/2023 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/3/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/18/2023 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/18/2023 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 12/18/2023 Approved HAMIK HARTOUNIAN
Insulation 12/18/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 1/12/2024 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/17/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 1/17/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/17/2024 Approved HAMIK HARTOUNIAN
Final 1/27/2025 Not Ready for Inspection THOMAS LOGRASSO
Final 4/9/2025 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 4/9/2025 Corrections Issued NICHOLAS LOPEZ
Final 6/12/2025 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 6/12/2025 Approved NICHOLAS LOPEZ
Final 8/12/2025 Corrections Issued BRENDAN MORELLI
Final 11/18/2025 OK to Issue CofO NICHOLAS LOPEZ