1901 S WESTWOOD BLVD 90025
Certificate Information: 1901 S WESTWOOD BLVD 90025
- Application / Permit
- 22016-10000-22405
- Plan Check / Job No.
- B22LA14739
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Veterinary Clinic
- Work Description
- Change of Use from Retail to Veterinary office
- Permit Issued
- Issued on 1/27/2023
- Issuing Office
- Current Status
- CofO Issued on 7/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | LARRY LEE |
| Corrections Issued | 8/1/2022 | LARRY LEE |
| Quality Review Completed | 8/10/2022 | LIPING TENG |
| Applicant returned to address corrections | 10/6/2022 | CARLOS MONTES |
| Plan Check Approved | 1/25/2023 | CARLOS MONTES |
| Issued | 1/27/2023 | APPLICANT |
| CofO in Progress | 7/24/2023 | PAUL DAVIDSON |
| Permit Finaled | 7/28/2023 | DAVID TSAU |
| Permit Finaled | 7/28/2023 | DAVID TSAU |
| CofO Issued | 7/28/2023 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 9/27/2022 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2022 | JEANIE LAM |
| DAS Clearance | Cleared | 12/6/2022 | Hernan Arreola |
| Specific Plan | Cleared | 12/12/2022 | FREDDY GARCIA |
| Sewer availability | Cleared | 12/21/2022 | CINDY QI |
| Comm Cor/Mini-Mall | Cleared | 12/22/2022 | DALIA MOKAYED |
Contact Information
| Contractor | Gray Wc; Lic. No.: 775947-B | , |
| Contractor | Gray West Construction Inc; Lic. No.: 775947-B | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2023 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 2/16/2023 | Conditional Approval | PAUL DAVIDSON |
| Deputy Other (see comments) | 2/16/2023 | Conditional Approval | PAUL DAVIDSON |
| Drywall Nailing | 3/3/2023 | Partial Inspection | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 3/3/2023 | Conditional Approval | SHAVONNE ESPINOZA |
| Light Gage Steel Frame | 3/3/2023 | Corrections Issued | SHAVONNE ESPINOZA |
| Pre-Inspection | 3/3/2023 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 3/15/2023 | Conditional Approval | PAUL DAVIDSON |
| Insulation | 4/5/2023 | Approved | PAUL DAVIDSON |
| Light Gage Steel Frame | 4/5/2023 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 4/14/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 4/19/2023 | Conditional Approval | PAUL DAVIDSON |
| Deputy Other (see comments) | 4/19/2023 | Conditional Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 5/17/2023 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 5/19/2023 | Approved | PAUL DAVIDSON |
| T-Bar Ceiling | 5/22/2023 | Conditional Approval | PAUL DAVIDSON |
| Final | 7/7/2023 | Not Ready for Inspection | SORIN CIRSTOIU |
| Green Building Final | 7/7/2023 | Not Ready for Inspection | SORIN CIRSTOIU |
| METHANE-Final | 7/7/2023 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 7/7/2023 | Not Ready for Inspection | SORIN CIRSTOIU |
| Pre-Inspection | 7/12/2023 | Approved | PAUL DAVIDSON |
| Final | 7/20/2023 | Conditional Approval | PAUL DAVIDSON |
| Green Building Final | 7/20/2023 | Approved | PAUL DAVIDSON |
| METHANE-Final | 7/20/2023 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 7/20/2023 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 7/20/2023 | Approved | PAUL DAVIDSON |