3543 S FEDERAL AVE 90066
Certificate Information: 3543 S FEDERAL AVE 90066
- Application / Permit
- 22016-10000-22379
- Plan Check / Job No.
- B22LA14719
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/6/2023
- Issuing Office
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2022 | SERGIO MUNIZ |
| Corrections Issued | 8/6/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 8/27/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/7/2022 | JEROME MAGAT PALMA |
| Issued | 1/6/2023 | APPLICANT |
| CofO in Progress | 7/31/2023 | RYAN BARNES |
| Permit Finaled | 8/8/2023 | JOHN MATTILLO |
| Permit Finaled | 9/6/2023 | BRUCE TODD |
| CofO Issued | 9/6/2023 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/25/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 11/30/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/23/2023 | Partial Approval | RYAN BARNES |
| Deputy Drilled-In Anchors | 2/8/2023 | Approved | RYAN BARNES |
| Pre-Inspection | 2/8/2023 | Partial Approval | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 2/9/2023 | Approved | RYAN BARNES |
| Footing/Foundation/Slab | 2/9/2023 | Approved | RYAN BARNES |
| Underground Mechanical | 2/9/2023 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 3/3/2023 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | RYAN BARNES |
| Green Building Rough | 3/6/2023 | Approved | RYAN BARNES |
| PLUMBING-Rough | 3/6/2023 | Approved | RYAN BARNES |
| Wood Frame | 3/6/2023 | Approved | RYAN BARNES |
| Insulation | 3/8/2023 | Approved | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2023 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 5/17/2023 | Partial Approval | RYAN BARNES |
| Drywall Nailing | 5/22/2023 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 5/22/2023 | Approved | RYAN BARNES |
| Shower Pan | 5/31/2023 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 6/15/2023 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 6/30/2023 | Corrections Issued | ANDREW BEELI |
| HVAC-Final | 6/30/2023 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 7/14/2023 | Corrections Issued | ANDREW BEELI |
| HVAC-Final | 7/14/2023 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 7/19/2023 | Approved | RYAN BARNES |
| Final | 7/19/2023 | Conditional Approval | RYAN BARNES |
| Green Building Final | 7/19/2023 | Approved | RYAN BARNES |
| PLUMBING-Final | 7/19/2023 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 7/19/2023 | Approved | RYAN BARNES |