3543 S FEDERAL AVE 90066

Certificate Information: 3543 S FEDERAL AVE 90066

Application / Permit
22016-10000-22379
Plan Check / Job No.
B22LA14719
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/6/2023
Issuing Office
Current Status
CofO Issued on 9/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2022 APPLICANT
Assigned to Plan Check Engineer 8/5/2022 SERGIO MUNIZ
Corrections Issued 8/6/2022 SERGIO MUNIZ
Applicant returned to address corrections 8/27/2022 JEROME MAGAT PALMA
Plan Check Approved 12/7/2022 JEROME MAGAT PALMA
Issued 1/6/2023 APPLICANT
CofO in Progress 7/31/2023 RYAN BARNES
Permit Finaled 8/8/2023 JOHN MATTILLO
Permit Finaled 9/6/2023 BRUCE TODD
CofO Issued 9/6/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 8/25/2022 COLIN LOREDO
Sewer availability Cleared 8/25/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/16/2022 COLIN LOREDO
Construction near power lines Cleared 11/30/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/23/2023 Partial Approval RYAN BARNES
Deputy Drilled-In Anchors 2/8/2023 Approved RYAN BARNES
Pre-Inspection 2/8/2023 Partial Approval RYAN BARNES
Excavation/Setback/Form/Re-Bar 2/9/2023 Approved RYAN BARNES
Footing/Foundation/Slab 2/9/2023 Approved RYAN BARNES
Underground Mechanical 2/9/2023 Approved RYAN BARNES
ELECTRICAL-Rough 3/3/2023 Approved RYAN BARNES
BUILDING-Rough-Frame 3/6/2023 Approved RYAN BARNES
Green Building Rough 3/6/2023 Approved RYAN BARNES
PLUMBING-Rough 3/6/2023 Approved RYAN BARNES
Wood Frame 3/6/2023 Approved RYAN BARNES
Insulation 3/8/2023 Approved RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Approved RYAN BARNES
Interior/Exterior Lathing 5/17/2023 Partial Approval RYAN BARNES
Drywall Nailing 5/22/2023 Approved RYAN BARNES
Interior/Exterior Lathing 5/22/2023 Approved RYAN BARNES
Shower Pan 5/31/2023 Approved RYAN BARNES
Interior/Exterior Lathing 6/15/2023 Approved RYAN BARNES
ELECTRICAL-Final 6/30/2023 Corrections Issued ANDREW BEELI
HVAC-Final 6/30/2023 Approved ANDREW BEELI
ELECTRICAL-Final 7/14/2023 Corrections Issued ANDREW BEELI
HVAC-Final 7/14/2023 Approved ANDREW BEELI
ELECTRICAL-Final 7/19/2023 Approved RYAN BARNES
Final 7/19/2023 Conditional Approval RYAN BARNES
Green Building Final 7/19/2023 Approved RYAN BARNES
PLUMBING-Final 7/19/2023 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved RYAN BARNES
Smoke Detectors 7/19/2023 Approved RYAN BARNES