3558 N HILLVIEW PL 90032
Certificate Information: 3558 N HILLVIEW PL 90032
- Application / Permit
- 22016-10000-22288
- Plan Check / Job No.
- B22LA14656
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF (E) 533 SF SINGLE STORY REIDENCE
- Permit Issued
- Issued on 9/9/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/28/2023
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | NGHI SU |
| Corrections Issued | 8/8/2022 | NGHI SU |
| Quality Review Completed | 8/11/2022 | FARUK SEZER |
| Building Plans Picked Up | 8/12/2022 | APPLICANT |
| Applicant returned to address corrections | 9/2/2022 | NGHI SU |
| Plan Check Approved | 9/2/2022 | NGHI SU |
| Issued | 9/9/2022 | APPLICANT |
| Permit Finaled-Status Void | 8/8/2023 | AMY COLIN |
| Re-Activate Permit | 8/10/2023 | AMY COLIN |
| Permit Finaled | 8/18/2023 | AMY COLIN |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/17/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 8/17/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | TREVOR QUAN |
| "D" conditions | Cleared | 8/23/2022 | MAYELA VILLA |
| "Q" conditions | Cleared | 8/23/2022 | MAYELA VILLA |
| ZI | Cleared | 8/23/2022 | MAYELA VILLA |
Contact Information
| Architect | Gonzalez,, David; Lic. No.: C34529 | 1719 MADISON AVENUE PASADENA, CA 91104 |
| Contractor | B M Construction Llc; Lic. No.: 1066119-B | 568 MT WASHINGTON DRIVE LOS ANGELES, CA 90065 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/14/2022 | Partial Approval | AMY COLIN |
| Pre-Inspection | 10/14/2022 | Partial Approval | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 11/4/2022 | Not Ready for Inspection | AMY COLIN |
| Footing/Foundation/Slab | 11/22/2022 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 1/27/2023 | Approved | AMY COLIN |
| Wood Frame | 2/22/2023 | Partial Approval | AMY COLIN |
| Insulation | 5/23/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 5/23/2023 | Partial Approval | AMY COLIN |
| Drywall Nailing | 5/25/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 5/25/2023 | Partial Approval | AMY COLIN |
| Interior/Exterior Lathing | 6/21/2023 | Approved | AMY COLIN |
| Final | 8/8/2023 | Conditional Approval | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 8/8/2023 | Approved | AMY COLIN |
| Wood Frame | 8/8/2023 | Approved | AMY COLIN |
| Final | 8/18/2023 | Permit Finaled | AMY COLIN |