2030 W 83RD ST 90047

Certificate Information: 2030 W 83RD ST 90047

Application / Permit
22016-10000-22181
Plan Check / Job No.
B22LA14617
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT 23'-0" X 20'-0" PORTION OF DETACHED GARAGE AND RECREATION ROOM INTO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) WITH ATTACHED ONE CAR GARAGE - NO CHANGE IN FLOOR AREA - PER ENGINEER
Permit Issued
Issued on 2/10/2023
Issuing Office
Current Status
CofO Issued on 7/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2022 APPLICANT
Assigned to Plan Check Engineer 7/29/2022 SELLA BENYAMIN
Corrections Issued 8/1/2022 SELLA BENYAMIN
Applicant returned to address corrections 8/15/2022 SELLA BENYAMIN
Plan Check Approved 2/6/2023 DANIEL ABRAMYAN
Issued 2/10/2023 APPLICANT
CofO in Progress 7/19/2023 ENRIQUE MIRELES
CofO in Progress 7/19/2023 ENRIQUE MIRELES
Permit Finaled 7/23/2023 DEROLD HAUFF
CofO Issued 7/23/2023 DEROLD HAUFF
Permit Finaled 7/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 12/5/2022 RIDWAN HARDY
Address approval Cleared 12/14/2022 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 1/25/2023 ERIK BEASLEY
Sewer availability Cleared 1/25/2023 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Lionel J; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2023 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 3/15/2023 Not Ready for Inspection ENRIQUE MIRELES
Sewer 3/15/2023 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 3/20/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/31/2023 Approved ENRIQUE MIRELES
Wood Frame 3/31/2023 Approved ENRIQUE MIRELES
Insulation 4/5/2023 Approved ENRIQUE MIRELES
Wood Frame 4/5/2023 Approved ENRIQUE MIRELES
Drywall Nailing 4/10/2023 Approved ENRIQUE MIRELES
Shower Pan 4/10/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/19/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/19/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/19/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/19/2023 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/19/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/28/2023 Approved ENRIQUE MIRELES
Final 5/17/2023 Corrections Issued ENRIQUE MIRELES
Final 6/7/2023 Corrections Issued ENRIQUE MIRELES
Final 6/16/2023 Corrections Issued ENRIQUE MIRELES
Final 6/27/2023 Conditional Approval ENRIQUE MIRELES
ELECTRICAL-Rough 7/7/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/13/2023 Approved ENRIQUE MIRELES
Final 7/18/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 7/18/2023 Approved ENRIQUE MIRELES