9042 W HARGIS ST 90034
Certificate Information: 9042 W HARGIS ST 90034
- Application / Permit
- 22016-10000-22180
- Plan Check / Job No.
- B22LA14615
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Converting existing two car garage to 360 sq ft ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/21/2023
- Issuing Office
- Current Status
- CofO Issued on 6/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/1/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 5/16/2023 | HANS SANTIAGO |
| Plan Check Approved | 7/13/2023 | ANDREW SANTIAGO |
| Issued | 7/21/2023 | APPLICANT |
| CofO in Progress | 6/3/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 6/13/2024 | DANIEL ORRANTE |
| CofO Issued | 6/13/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/13/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2022 | CINDY QI |
| Sewer availability | Cleared | 8/29/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2022 | CINDY QI |
| Construction near power lines | Cleared | 5/7/2023 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 7/7/2023 | ROBERT HUGHES |
Contact Information
| Contractor | Mae Cm Services Inc; Lic. No.: 886471-B | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/11/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Deputy Drilled-In Anchors | 9/12/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Pre-Inspection | 9/12/2023 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/20/2023 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Drilled-In Anchors | 9/21/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 9/25/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 9/26/2023 | Approved | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 10/5/2023 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 10/17/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Wood Frame | 10/17/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 2/1/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 2/7/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 2/22/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/22/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/29/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 2/29/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 4/19/2024 | Approved | MEL KHACHATOURIAN |
| Final | 4/19/2024 | Corrections Issued | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 4/19/2024 | Partial Approval | MEL KHACHATOURIAN |
| Final | 5/23/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 5/23/2024 | Approved | MEL KHACHATOURIAN |
| Gas Test | 5/29/2024 | Approved | MEL KHACHATOURIAN |