2239 N SHOREDALE AVE 90031
Certificate Information: 2239 N SHOREDALE AVE 90031
- Application / Permit
- 22016-10000-22178
- Plan Check / Job No.
- B22LA14614
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/19/2022
- Issuing Office
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | DANIEL YIP |
| Corrections Issued | 7/31/2022 | DANIEL YIP |
| Applicant returned to address corrections | 8/11/2022 | DANIEL YIP |
| Plan Check Approved | 10/14/2022 | DANIEL YIP |
| Issued | 10/19/2022 | APPLICANT |
| CofO in Progress | 9/23/2024 | THOMAS LOGRASSO |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
| CofO Issued | 9/25/2024 | RUBEN SALAS |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/8/2022 | JEANIE LAM |
| Sewer availability | Cleared | 8/8/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 10/12/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/12/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/30/2022 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 12/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/8/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Underground Mechanical | 2/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 2/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/6/2023 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 2/6/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/6/2023 | Approved | THOMAS LOGRASSO |
| Wood Frame | 2/6/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 2/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 2/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/22/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/22/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 2/22/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/22/2023 | Partial Approval | STUART CHAPMAN |
| MERV13>=Rough | 2/22/2023 | Approved | STUART CHAPMAN |
| Insulation | 2/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 3/9/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 3/30/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/17/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/18/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Final | 9/18/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| MERV13>=Final | 9/18/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 9/18/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/29/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 4/29/2024 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/29/2024 | SGSOV Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 6/7/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 6/7/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 6/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/3/2024 | Not Ready for Inspection | ROY SPAULDING |
| Final | 9/3/2024 | Not Ready for Inspection | ROY SPAULDING |
| MERV13>=Final | 9/3/2024 | Approved | ROY SPAULDING |
| Final | 9/6/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/19/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 9/19/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 9/23/2024 | OK to Issue CofO | THOMAS LOGRASSO |