547 W 99TH ST 90044

Certificate Information: 547 W 99TH ST 90044

Application / Permit
22016-10000-22164
Plan Check / Job No.
B22LA14602
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT EXISTING 2-CAR GARAGE INTO ADU PER STATE LAW ALL WORK DONE PER WFPP
Permit Issued
Issued on 12/13/2022
Issuing Office
Current Status
CofO Issued on 7/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2022 APPLICANT
Assigned to Plan Check Engineer 8/2/2022 JOSEPH RAFOLS
Corrections Issued 8/3/2022 JOSEPH RAFOLS
Plan Check Approved 12/9/2022 KHUONG TRUONG
Issued 12/13/2022 APPLICANT
CofO in Progress 7/7/2023 JAMES CHAVEZ
Permit Finaled 7/7/2023 ANSON MAGLASANG
CofO Issued 7/7/2023 ANSON MAGLASANG
Permit Finaled 7/7/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/18/2022 AMAAN MALIK
Sewer availability Cleared 11/18/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/2/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/17/2023 Not Ready for Inspection JULIAN AMAYA
Footing/Foundation/Slab 1/17/2023 Corrections Issued JULIAN AMAYA
PLUMBING-Rough 1/17/2023 Not Ready for Inspection JULIAN AMAYA
PLUMBING-Rough 2/1/2023 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 2/3/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 2/16/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 2/27/2023 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 2/27/2023 Corrections Issued JAMES CHAVEZ
Green Building Rough 2/27/2023 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 2/27/2023 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 3/1/2023 Approved JAMES CHAVEZ
HVAC-Rough 3/1/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 3/1/2023 Approved JAMES CHAVEZ
Green Building Rough 3/7/2023 Approved JAMES CHAVEZ
Insulation 3/10/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Approved JAMES CHAVEZ
Drywall Nailing 3/16/2023 Approved JAMES CHAVEZ
Underground Mechanical 4/7/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 4/20/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 4/20/2023 Corrections Issued JAMES CHAVEZ
Final 4/20/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 4/20/2023 Corrections Issued JAMES CHAVEZ
PLUMBING-Final 4/20/2023 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 4/20/2023 Not Ready for Inspection JAMES CHAVEZ
Final 5/18/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 5/18/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 5/18/2023 Approved JAMES CHAVEZ
Service/Power Release 5/19/2023 Approved JAMES CHAVEZ
Final 5/23/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 5/23/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Approved JAMES CHAVEZ
Final 5/26/2023 OK to Issue CofO JAMES CHAVEZ