12902 W LUCILLE AVE 90066

Certificate Information: 12902 W LUCILLE AVE 90066

Application / Permit
22016-10000-22144
Plan Check / Job No.
B22LA14589
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: CONVERT (E) ATTACHED GARAGE AND STORAGE IN 2-STORY DUPLEX TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 9/1/2022
Issuing Office
Current Status
CofO Issued on 4/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2022 APPLICANT
Assigned to Plan Check Engineer 7/29/2022 DANIEL YIP
Corrections Issued 7/31/2022 DANIEL YIP
Plan Check Approved 9/1/2022 DANIEL YIP
Issued 9/1/2022 APPLICANT
CofO in Progress 4/24/2023 RICHARD STEINBACH
Permit Finaled 4/24/2023 DANIEL ORRANTE
CofO Issued 4/24/2023 DANIEL ORRANTE
Permit Finaled 4/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Tenant Habitability Plan Cleared 8/2/2022 RICARDO BOHORQUEZ
Address approval Cleared 8/8/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 8/8/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/11/2022 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 8/29/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/14/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 10/14/2022 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 10/18/2022 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 10/18/2022 Partial Approval ANDREW NAVE
Deputy Drilled-In Anchors 10/19/2022 No Access for Inspection DAVID FEILER
Footing/Foundation/Slab 10/20/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 11/17/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 11/17/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 11/17/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/22/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Approved JESUS RODRIGUEZ
Green Building Rough 11/22/2022 Approved JESUS RODRIGUEZ
Insulation 11/22/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/22/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 12/1/2022 Approved JESUS RODRIGUEZ
Final 12/28/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 12/28/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 4/4/2023 Approved JESUS RODRIGUEZ
Final 4/4/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 4/4/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 4/4/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Approved JESUS RODRIGUEZ
Final 4/21/2023 Partial Approval JESUS RODRIGUEZ