109 S CRESCENT HEIGHTS BLVD 90048
Certificate Information: 109 S CRESCENT HEIGHTS BLVD 90048
- Application / Permit
- 22016-10000-22035
- Plan Check / Job No.
- B22LA14509
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan INTERIOR REMODEL TO (E) SFD
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/24/2024
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2022 | RACHEL BEYENE |
| Corrections Issued | 7/26/2022 | RACHEL BEYENE |
| Plan Check Approved | 7/30/2022 | FERNANDO FLORES |
| Issued | 9/28/2022 | APPLICANT |
| Permit Finaled | 7/24/2024 | MEL KHACHATOURIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Mozannar Construction Inc; Lic. No.: 695817-B | , |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 560 31ST ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/26/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 5/3/2023 | Approved | JEREMY TODD |
| Deputy Drilled-In Anchors | 5/4/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 6/12/2023 | Not Ready for Inspection | JEREMY TODD |
| ELECTRICAL-Rough | 6/12/2023 | Not Ready for Inspection | JEREMY TODD |
| HVAC-Rough | 6/12/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 6/12/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/14/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/14/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/14/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 7/25/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 8/4/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/4/2023 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 8/4/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/15/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 12/15/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Final | 12/15/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 3/27/2024 | Corrections Issued | SEAN HAUPT |
| HVAC-Final | 3/27/2024 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 3/27/2024 | Approved | SEAN HAUPT |
| Smoke Detectors | 3/27/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 3/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| Final | 3/29/2024 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Rough | 3/29/2024 | Approved | MEL KHACHATOURIAN |
| Final | 4/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Final | 5/10/2024 | Corrections Issued | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Final | 6/3/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 7/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| Final | 7/24/2024 | Permit Finaled | MEL KHACHATOURIAN |