740 S ALVARADO ST # 100 90057
Certificate Information: 740 S ALVARADO ST # 100 90057
- Application / Permit
- 22016-10000-21994
- Plan Check / Job No.
- B22LA14471
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE FROM RESTURANT TO OFFICE, TENANT IMPROVEMENT, NEW INTERIOR PARTITIONS, SUSPENDED CEILINGS, FINISHES.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Current Status
- CofO Issued on 10/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 8/8/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 8/9/2022 | PETER KIM |
| Applicant returned to address corrections | 9/9/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 9/16/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 9/29/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 10/13/2022 | ARMEN JIVALAGIAN |
| Plan Check Approved | 2/3/2023 | ARMEN JIVALAGIAN |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 10/6/2023 | KATY RAMIREZ |
| CofO Issued | 10/11/2023 | ERNESTO CORRAL |
| Permit Finaled | 10/11/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/28/2022 | Hernan Arreola |
| Green Code | Cleared | 1/13/2023 | KHEDER ALRAZAA |
| ZA Case | Cleared | 1/17/2023 | JAZMIN ROQUE |
| Historic Resource Verification | Cleared | 1/23/2023 | MAX LODER |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/24/2023 | AMAAN MALIK |
| Food Service Establishment | Cleared | 1/25/2023 | KENNETH BROWNE |
| Redevelopment Project Area | Cleared | 1/25/2023 | GRACIELA ACOSTA |
Contact Information
| Architect | Geronaga,, Rhodore Candelaria; Lic. No.: C24750 | 7267 EAST DRAKE DRIVE ANAHEIM HILLS, CA 92807 |
| Contractor | Redesign Group Inc; Lic. No.: 746670-B | 14546 1/2 MOORPARK STREET SHERMAN OAKS, CA 91403 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/6/2023 | Approved | RAMAZANALI ALMASI |
| Deputy Drilled-In Anchors | 4/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 4/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 4/14/2023 | Corrections Issued | KATY RAMIREZ |
| Insulation | 4/19/2023 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 4/19/2023 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 4/21/2023 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 5/12/2023 | Corrections Issued | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 5/16/2023 | Approved | RAMAZANALI ALMASI |
| Deputy Reinf. Concrete | 5/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| T-Bar Ceiling | 5/18/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 9/27/2023 | Partial Inspection | KATY RAMIREZ |
| Green Building Final | 9/27/2023 | Approved | KATY RAMIREZ |
| Green Building Rough | 9/27/2023 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 9/27/2023 | Approved | KATY RAMIREZ |
| Final | 10/6/2023 | OK to Issue CofO | KATY RAMIREZ |