8335-8337 N WHITE OAK AVE 91325
Certificate Information: 8335-8337 N WHITE OAK AVE 91325
- Application / Permit
- 22016-10000-21961
- Plan Check / Job No.
- B22VN10794
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: CONVERT (E) 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE TO 1-STORY SINGLE FAMILY DWELLING WITH JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 12/8/2022
- Issuing Office
- Current Status
- CofO Issued on 4/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2022 | DANIEL YIP |
| Corrections Issued | 7/24/2022 | DANIEL YIP |
| Quality Review Completed | 7/25/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/23/2022 | DANIEL YIP |
| Plan Check Approved | 12/8/2022 | DANIEL YIP |
| Issued | 12/8/2022 | APPLICANT |
| CofO in Progress | 3/11/2024 | JAVIER RAMOS JR |
| Permit Finaled | 4/5/2024 | RUBEN SALAS |
| CofO Issued | 4/5/2024 | RUBEN SALAS |
| Permit Finaled | 4/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2022 | ROMAN GUTIERREZ |
| Miscellaneous | Cleared | 12/8/2022 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/12/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/25/2023 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/2/2023 | No Access for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/2/2023 | No Access for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 2/2/2023 | No Access for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/2/2023 | No Access for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/3/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/3/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/3/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/3/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 2/21/2023 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 2/24/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 4/10/2023 | Approved | WILLIAM WREN |
| Shower Pan | 4/10/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/6/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/6/2023 | Partial Inspection | JAVIER RAMOS JR |
| Final | 12/6/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 12/6/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 12/6/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| Final | 1/9/2024 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/9/2024 | Approved | JAVIER RAMOS JR |
| Final | 1/22/2024 | Corrections Issued | JAVIER RAMOS JR |
| Final | 3/11/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 3/11/2024 | Approved | JAVIER RAMOS JR |