3216 S HILL ST 90007
Certificate Information: 3216 S HILL ST 90007
- Application / Permit
- 22016-10000-21888
- Plan Check / Job No.
- B22LA14378
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Take Out
- Work Description
- CHANGE OF USE FROM (E) OFFICE/COFFEE ROASTING TO OFFICE/COFFEE ROASTING/TAKE OUT TENANT IMPROVEMENT. INSTALLATION OF NEW COMMERICAL EQUIPMENT FOR TAKE OUT WINDOW.
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2022 | JOSEPH RAFOLS |
| Corrections Issued | 7/22/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 12/21/2022 | DANIEL SANJUAN |
| Plan Check Approved | 12/22/2022 | ZAW HAN |
| Issued | 12/22/2022 | APPLICANT |
| CofO in Progress | 8/28/2023 | ALAN MORELOS |
| CofO Issued | 9/15/2023 | TED RIES |
| Permit Finaled | 9/15/2023 | TED RIES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2022 | CHRISTOPHER ROCHA |
| Hold | Cleared | 12/2/2022 | GRACE PANGILINAN |
| Sewer availability | Cleared | 12/2/2022 | CHRISTOPHER ROCHA |
| Historic Resource Verification | Cleared | 12/12/2022 | MAX LODER |
| Food Service Establishment | Cleared | 12/13/2022 | RAMESHBHAIR PATEL |
| Redevelopment Project Area | Cleared | 12/13/2022 | DAVID URITA |
| Encroachment in public way | Cleared | 12/21/2022 | JEREMY CHOK |
| Food establishment approval | Cleared | 12/21/2022 | LACDHS APPROVED |
Contact Information
| Contractor | D R Construction; Lic. No.: 826773-B | 727 BRIDEWELL ST LOS ANGELES, CA 90042 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/28/2022 | Partial Inspection | ALAN MORELOS |
| Drywall Nailing | 1/9/2023 | Approved | ALAN MORELOS |
| Final | 5/17/2023 | Not Ready for Inspection | ALAN MORELOS |
| METHANE-Final | 5/17/2023 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 5/17/2023 | SGSOV Approved | ALAN MORELOS |
| Smoke Detectors | 5/17/2023 | Approved | ALAN MORELOS |
| Final | 8/3/2023 | Not Ready for Inspection | ALAN MORELOS |
| Final | 8/10/2023 | Conditional Approval | ALAN MORELOS |
| Final | 8/28/2023 | OK to Issue CofO | ALAN MORELOS |