749-751 S COLUMBIA AVE 90017
Certificate Information: 749-751 S COLUMBIA AVE 90017
- Application / Permit
- 22016-10000-21791
- Plan Check / Job No.
- B22LA14295
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- Combination permit to convert exsiting attached garage to JADU (391 SF) per LAMC 12.22A33(c) & (e) JADU address is 749 1/2 Columbia Ave**
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Metro
- Current Status
- Issued on 7/27/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | JOSEPH RAFOLS |
| Corrections Issued | 7/21/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 7/27/2022 | JOSEPH RAFOLS |
| Issued | 7/27/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | JEANIE LAM |
| Historic Resource Verification | Cleared | 7/25/2022 | MAX LODER |
| Sewer availability | Cleared | 7/25/2022 | JEANIE LAM |
| Redevelopment Project Area | Cleared | 7/26/2022 | GRACIELA ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/17/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Pre-Inspection | 10/6/2022 | No Access for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/23/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/23/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 12/23/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 12/23/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 12/23/2022 | Approved | STUART CHAPMAN |
| Insulation | 12/29/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/29/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 1/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/10/2023 | Not Ready for Inspection | JULIAN AMAYA |
| Drywall Nailing | 1/11/2023 | Approved | JULIAN AMAYA |
| ELECTRICAL-Final | 11/4/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 11/4/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 11/4/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| HVAC-Final | 11/4/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| PLUMBING-Final | 11/4/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Not Ready | WILLIAM SIERRA |
| Smoke Detectors | 11/4/2025 | Not Ready for Inspection | WILLIAM SIERRA |