2736 E POMEROY AVE 90033
Certificate Information: 2736 E POMEROY AVE 90033
- Application / Permit
- 22016-10000-21697
- Plan Check / Job No.
- B22LA14232
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing attached Rec Room into two one Bedroom ADUs (416 and 398 SF respectively)in existing apartment
- Permit Issued
- Issued on 5/26/2023
- Issuing Office
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 7/31/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/2/2022 | GARO TELMI |
| Plan Check Approved | 10/17/2022 | ARSALAN SHABESTARI |
| Issued | 5/26/2023 | APPLICANT |
| CofO in Progress | 3/19/2024 | RONALD JIMENEZ |
| Permit Finaled | 3/19/2024 | ERNESTO CORRAL |
| CofO Issued | 3/19/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZA Case | Cleared | 8/3/2022 | RYAN LY |
| ZA Case | Cleared | 8/3/2022 | RYAN LY |
| Address approval | Cleared | 8/10/2022 | JEANIE LAM |
| Sewer availability | Cleared | 8/10/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 8/15/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Fort Multifamily Inc; Lic. No.: 1097435-B | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Partial Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/20/2023 | Partial Inspection | OSVALDO PARAMO |
| Wood Frame | 7/20/2023 | Partial Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Partial Inspection | AMY COLIN |
| Interior/Exterior Lathing | 7/31/2023 | Partial Inspection | AMY COLIN |
| Wood Frame | 7/31/2023 | Partial Inspection | AMY COLIN |
| Wood Frame | 8/8/2023 | Partial Approval | TED RIES |
| Insulation | 9/7/2023 | Partial Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/7/2023 | Partial Inspection | OSVALDO PARAMO |
| Insulation | 9/13/2023 | Approved | JULIAN CAPUCETTI |
| Interior/Exterior Lathing | 9/13/2023 | Approved | JULIAN CAPUCETTI |
| Drywall Nailing | 9/18/2023 | Approved | RAFAEL CORTES |
| Drywall Nailing | 9/19/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 12/4/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 12/4/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 12/4/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 3/7/2024 | Conditional Approval | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Not Required | RONALD JIMENEZ |
| Smoke Detectors | 3/7/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 3/7/2024 | Approved | RONALD JIMENEZ |
| Final | 3/19/2024 | OK to Issue CofO | RONALD JIMENEZ |