940 S MAGNOLIA AVE UNITS A-E 90006

Certificate Information: 940 S MAGNOLIA AVE UNITS A-E 90006

Application / Permit
22016-10000-21172
Plan Check / Job No.
B22LA13946
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert existing attached garage (12 parking spaces) into 5 ADUs
Permit Issued
Issued on 10/19/2022
Issuing Office
Current Status
CofO Issued on 3/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/22/2022 JOE VO
Corrections Issued 7/23/2022 JOE VO
Quality Review Completed 7/26/2022 GARO TELMI
Applicant returned to address corrections 8/24/2022 JOE VO
Plan Check Approved 10/18/2022 JOE VO
Issued 10/19/2022 APPLICANT
CofO in Progress 3/21/2025 ERNESTO CORRAL
Permit Finaled 3/21/2025 ERNESTO CORRAL
CofO Issued 3/21/2025 ERNESTO CORRAL
Permit Finaled 3/21/2025 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 8/12/2022 RICARDO BOHORQUEZ
Address approval Cleared 8/18/2022 CELINA MORENO
Sewer availability Cleared 8/18/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/19/2022 CELINA MORENO
Hydrant and Access approval Cleared 9/24/2022 GILBERT URREA
Miscellaneous Cleared 10/18/2022 JOE VO

Contact Information

Contractor K3m Building Contractors Inc; Lic. No.: 1046266-B       ,
Engineer Abdelhafeez,, Haitham Abbas; Lic. No.: NA63359       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/18/2023 Partial Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 7/6/2023 Approved RAMAZANALI ALMASI
Green Building Rough 10/2/2024 Partial Approval PAUL BAZERKANIAN
Wood Frame 10/2/2024 Partial Approval PAUL BAZERKANIAN
Insulation 10/15/2024 Partial Approval PAUL BAZERKANIAN
Interior/Exterior Lathing 10/15/2024 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 10/21/2024 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 10/22/2024 Approved JEROME BLACKWOOD
Final 2/27/2025 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 2/27/2025 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 2/27/2025 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 2/27/2025 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 2/27/2025 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 2/27/2025 Not Ready for Inspection JEROME BLACKWOOD
Final 3/20/2025 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 3/20/2025 Approved JEROME BLACKWOOD
Green Building Rough 3/20/2025 Approved JEROME BLACKWOOD
Smoke Detectors 3/20/2025 Approved JEROME BLACKWOOD
Wood Frame 3/20/2025 Approved JEROME BLACKWOOD
Final 3/21/2025 OK to Issue CofO ERNESTO CORRAL