11916 W PICO BLVD 90064

Certificate Information: 11916 W PICO BLVD 90064

Application / Permit
22016-10000-21045
Plan Check / Job No.
B22LA13866
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
ePLAN. CONVERT (E) RETAIL INTO 2 ADDITIONAL DWELLING UNITS AND A COMMUNITY ROOM.
Permit Issued
Issued on 8/25/2023
Issuing Office
Current Status
CofO Issued on 4/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/22/2022 KEVIN MORALES
Corrections Issued 7/23/2022 KEVIN MORALES
Quality Review Completed 7/28/2022 EUGENE BARBEAU
Plan Check Approved 2/9/2023 KEVIN MORALES
Issued 8/25/2023 APPLICANT
CofO in Progress 4/18/2025 FARHAD DADBIN
Permit Finaled 4/25/2025 DAVID TSAU
CofO Issued 4/25/2025 DAVID TSAU
Permit Finaled 4/25/2025 DAVID TSAU

Permit Application Clearance Information

Miscellaneous Cleared 8/1/2022 RUBEN VASQUEZ
Address approval Cleared 8/3/2022 ANTHONY MAINEZ
CPC Cleared 10/17/2022 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 12/12/2022 ANTHONY MAINEZ
Sewer availability Cleared 12/12/2022 ANTHONY MAINEZ
Fire Marshal Fire Life Safety Cleared 12/14/2022 DOMINIQUE MEDINA
Density Bonus Cleared 2/3/2023 LOUIE MILLER

Contact Information

Contractor R C I Builders Inc; Lic. No.: 835114-B 2985 E HILLCREST DR #107      THOUSAND OAKS, CA 91362

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 12/8/2023 Not Ready for Inspection FARHAD DADBIN
Light Gage Steel Frame 1/24/2024 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 3/20/2024 Partial Approval FARHAD DADBIN
Insulation 3/26/2024 Approved FARHAD DADBIN
Drywall Nailing 4/9/2024 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 4/17/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 4/18/2024 Approved FARHAD DADBIN
Light Gage Steel Frame 10/29/2024 Partial Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 3/17/2025 Not Ready for Inspection FARHAD DADBIN
Final 4/10/2025 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Approved FARHAD DADBIN
Smoke Detectors 4/10/2025 Approved FARHAD DADBIN
Final 4/18/2025 OK to Issue CofO FARHAD DADBIN