4501 W FINLEY AVE 90027
Certificate Information: 4501 W FINLEY AVE 90027
- Application / Permit
- 22016-10000-20981
- Plan Check / Job No.
- B22LA13860
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- Elan: Soft-Story seismic retrofit per LABC Chapter 93: Install 6 Special Steel Cantilever Columns
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Current Status
- CofC Issued on 12/18/2023
Permit Application Status History
| Submitted | 7/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | HANS SANTIAGO |
| Corrections Issued | 8/1/2022 | HANS SANTIAGO |
| Quality Review Completed | 8/1/2022 | LIPING TENG |
| Plan Check Approved | 11/2/2022 | ANDREW SANTIAGO |
| Issued | 12/20/2022 | APPLICANT |
| OK for CofC | 9/21/2023 | VAHE KELEDJIAN |
| CofC Issued | 12/18/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/19/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/30/2023 | Not Ready for Inspection | JAIME RIOS |
| Wood Frame | 1/30/2023 | Not Ready for Inspection | JAIME RIOS |
| Wood Frame | 1/31/2023 | Not Ready for Inspection | JAIME RIOS |
| Wood Frame | 2/1/2023 | Conditional Approval | JAIME RIOS |
| Footing/Foundation/Slab | 2/16/2023 | Corrections Issued | VAHE KELEDJIAN |
| Structural Steel Frame | 2/16/2023 | Corrections Issued | VAHE KELEDJIAN |
| Wall Anchors | 2/16/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Wood Frame | 2/16/2023 | Corrections Issued | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 2/24/2023 | Conditional Approval | JAIME RIOS |
| Structural Steel Frame | 2/24/2023 | Conditional Approval | JAIME RIOS |
| Wood Frame | 2/24/2023 | Conditional Approval | JAIME RIOS |
| Deputy Reinf. Concrete | 2/28/2023 | Conditional Approval | JAIME RIOS |
| Drywall Nailing | 3/9/2023 | Approved | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 3/9/2023 | Approved | VAHE KELEDJIAN |
| Final | 9/21/2023 | OK for CofC | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 9/21/2023 | Approved | VAHE KELEDJIAN |