1546 S MIDVALE AVE 90024
Certificate Information: 1546 S MIDVALE AVE 90024
- Application / Permit
- 22016-10000-20770
- Plan Check / Job No.
- B22LA13725
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE TO ADU PER CA GC 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/29/2022
- Issuing Office
- Current Status
- CofO Issued on 4/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2022 | VIVIAN LAO |
| Corrections Issued | 7/21/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 9/14/2022 | VIVIAN LAO |
| Plan Check Approved | 9/16/2022 | VIVIAN LAO |
| Issued | 9/29/2022 | APPLICANT |
| CofO in Progress | 3/22/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 4/23/2024 | DANIEL ORRANTE |
| CofO Issued | 4/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 7/25/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/25/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2022 | ANTHONY MAINEZ |
| Miscellaneous | Cleared | 8/1/2022 | RAYMOND MUGAMBWA |
| Specific Plan | Cleared | 8/1/2022 | PEDRO AYALA |
| Construction near power lines | Cleared | 9/7/2022 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 9/14/2022 | VIVIAN LAO |
Contact Information
| Architect | Ryder,, Derek Thomas; Lic. No.: C32847 | 4111 GLENALBYN DRIVE LOS ANGELES, CA 90065 |
| Contractor | Skyson Construction Co; Lic. No.: 515183-B | 17609 VENTURA BLVD #218 ENCINO, CA 91316 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2022 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 12/16/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/29/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 4/13/2023 | Not Ready for Inspection | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 4/13/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 4/13/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 4/19/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 4/24/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/2/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 5/2/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/2/2023 | Partial Approval | JESUS PINEDA |
| METHANE-Rough | 5/2/2023 | Approved | JESUS PINEDA |
| Insulation | 5/11/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 5/26/2023 | Approved | BRENDAN LOONEY |
| Special/Order Compliance | 7/26/2023 | Partial Approval | DAVID FEILER |
| Shower Pan | 8/21/2023 | No Access for Inspection | ARAM AVEDISIAN |
| Shower Pan | 8/23/2023 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/6/2023 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 11/30/2023 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 11/30/2023 | Approved | BEN MOLSTAD |
| Final | 3/4/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 3/4/2024 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Not Required | ASHLEY THOMPSON |
| Smoke Detectors | 3/4/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 3/14/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/20/2024 | Approved | STEPHANIE SWANSON |
| Final | 3/20/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 3/20/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 3/20/2024 | Approved | STEPHANIE SWANSON |
| Final | 3/22/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |