1546 S MIDVALE AVE 90024

Certificate Information: 1546 S MIDVALE AVE 90024

Application / Permit
22016-10000-20770
Plan Check / Job No.
B22LA13725
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE TO ADU PER CA GC 65852.2(e)(1)(A)
Permit Issued
Issued on 9/29/2022
Issuing Office
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2022 APPLICANT
Assigned to Plan Check Engineer 7/20/2022 VIVIAN LAO
Corrections Issued 7/21/2022 VIVIAN LAO
Applicant returned to address corrections 9/14/2022 VIVIAN LAO
Plan Check Approved 9/16/2022 VIVIAN LAO
Issued 9/29/2022 APPLICANT
CofO in Progress 3/22/2024 OGANES TARAKHCHYAN
Permit Finaled 4/23/2024 DANIEL ORRANTE
CofO Issued 4/23/2024 DANIEL ORRANTE
Permit Finaled 4/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/25/2022 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 7/25/2022 ANTHONY MAINEZ
Sewer availability Cleared 7/25/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/27/2022 ANTHONY MAINEZ
Miscellaneous Cleared 8/1/2022 RAYMOND MUGAMBWA
Specific Plan Cleared 8/1/2022 PEDRO AYALA
Construction near power lines Cleared 9/7/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 9/14/2022 VIVIAN LAO

Contact Information

Architect Ryder,, Derek Thomas; Lic. No.: C32847 4111 GLENALBYN DRIVE      LOS ANGELES, CA 90065
Contractor Skyson Construction Co; Lic. No.: 515183-B 17609 VENTURA BLVD #218      ENCINO, CA 91316
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2022 Approved OGANES TARAKHCHYAN
Underground Mechanical 12/16/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Not Ready for Inspection CLAYTON GRAHAM
PLUMBING-Rough 3/29/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 4/13/2023 Not Ready for Inspection JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Approved JEREMY TODD
HVAC-Rough 4/13/2023 Approved JEREMY TODD
PLUMBING-Rough 4/13/2023 Approved JEREMY TODD
ELECTRICAL-Rough 4/19/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Rough 4/24/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/2/2023 Approved JESUS PINEDA
Green Building Rough 5/2/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 5/2/2023 Partial Approval JESUS PINEDA
METHANE-Rough 5/2/2023 Approved JESUS PINEDA
Insulation 5/11/2023 Approved JEREMY TODD
Drywall Nailing 5/26/2023 Approved BRENDAN LOONEY
Special/Order Compliance 7/26/2023 Partial Approval DAVID FEILER
Shower Pan 8/21/2023 No Access for Inspection ARAM AVEDISIAN
Shower Pan 8/23/2023 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 9/6/2023 Approved BEN MOLSTAD
ELECTRICAL-Rough 11/30/2023 Approved BEN MOLSTAD
Special/Order Compliance 11/30/2023 Approved BEN MOLSTAD
Final 3/4/2024 Corrections Issued ASHLEY THOMPSON
Green Building Final 3/4/2024 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Not Required ASHLEY THOMPSON
Smoke Detectors 3/4/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Final 3/14/2024 Corrections Issued STEPHANIE SWANSON
Green Building Final 3/14/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Final 3/20/2024 Approved STEPHANIE SWANSON
Final 3/20/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Final 3/20/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 3/20/2024 Approved STEPHANIE SWANSON
Final 3/22/2024 OK to Issue CofO OGANES TARAKHCHYAN