Pre-Inspection
|
9/27/2023
|
Approved
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
10/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
10/18/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
10/19/2023
|
No Access for Inspection
|
JEROME BLACKWOOD
|
|
Deputy Steel/Welding
|
10/20/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Structural Steel Frame
|
10/20/2023
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/25/2023
|
Partial Approval
|
RONALD JIMENEZ
|
|
Deputy Drilled-In Anchors
|
10/27/2023
|
No Result Entered
|
ADAM BURGESS
|
|
Deputy Wood Construction
|
10/30/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
10/31/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
11/1/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
11/2/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
11/7/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
11/8/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Reinf. Concrete
|
11/9/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
11/9/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
11/13/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
11/14/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
11/15/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Drilled-In Anchors
|
2/27/2024
|
Conditional Approval
|
RAFAEL CORTES
|
|
Deputy Steel/Welding
|
3/13/2024
|
Conditional Approval
|
RAFAEL CORTES
|
|
Deputy Reinf. Masonry
|
3/14/2024
|
Conditional Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
6/21/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Excavation/Setback/Form/Re-Bar
|
6/27/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
7/10/2024
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Masonry Wall/Backfill
|
7/10/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Reinforced Masonry Frame
|
7/10/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
7/15/2024
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
7/16/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
7/25/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
7/31/2024
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Masonry Wall/Backfill
|
8/2/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
9/13/2024
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
9/13/2024
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
10/15/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
10/17/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
11/27/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
12/10/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
12/16/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Light Gage Steel Frame
|
12/16/2024
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
Structural Steel Frame
|
12/16/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Wood Frame
|
12/16/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Excavation/Setback/Form/Re-Bar
|
12/17/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/17/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Excavation/Setback/Form/Re-Bar
|
1/3/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
1/7/2025
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
Excavation/Setback/Form/Re-Bar
|
1/13/2025
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
Excavation/Setback/Form/Re-Bar
|
1/14/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Structural Steel Frame
|
4/4/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
4/21/2025
|
No Access for Inspection
|
LUIS CCAMACHO
|
|
Light Gage Steel Frame
|
4/23/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Excavation/Setback/Form/Re-Bar
|
6/4/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Light Gage Steel Frame
|
6/12/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Insulation
|
7/2/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
7/15/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Excavation/Setback/Form/Re-Bar
|
8/11/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
8/13/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
8/26/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Light Gage Steel Frame
|
10/1/2025
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
11/13/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
12/12/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Special/Order Compliance
|
12/12/2025
|
Partial Inspection
|
REGINA MENDEZ
|
|
Reinforced Concrete Frame
|
12/17/2025
|
Partial Approval
|
LUIS CCAMACHO
|
|
Structural Steel Frame
|
12/30/2025
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
1/8/2026
|
Partial Approval
|
LUIS CCAMACHO
|
|
Final
|
1/14/2026
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
Green Building Final
|
1/14/2026
|
Approved
|
LUIS CCAMACHO
|
|
SGSOV-Seismic Gas S/O Valve
|
1/14/2026
|
SGSOV Approved
|
LUIS CCAMACHO
|
|
Smoke Detectors
|
1/14/2026
|
Approved
|
LUIS CCAMACHO
|
|
Final
|
1/30/2026
|
Corrections Issued
|
LUIS CCAMACHO
|
|
Final
|
2/24/2026
|
OK to Issue CofO
|
LUIS CCAMACHO
|