2161 W COLORADO BLVD 90041
Certificate Information: 2161 W COLORADO BLVD 90041
- Application / Permit
- 22016-10000-20708
- Plan Check / Job No.
- B22LA13651
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePlan SECTOR SCOPE OF WORK: • INSTALL (6) PROPOSED PANEL ANTENNAS (2 PER SECTOR) • INSTALL (3) PROPOSED ANTENNA MOUNTS • INSTALL PROPOSED JUMPERS • INSTALL (12) PROPOSED RRHs (4 PER SECTOR) • INSTALL (3) PROPOSED OVER VOLTAGE PROTECTION DEVICE (OVP) (1 PER SECTOR) • INSTALL (3) PROPOSED HYBRID CABLES • INSTALL PROPOSED CABLE TRAYS ROOFTOP SCOPE OF WORK: • INSTALL (1) PROPOSED METAL PLATFORM WITH H-FRAME • INSTALL (1) PROPOSED CABLE TRAY • INSTALL (1) PROPOSED BBU IN CABINET • INSTALL (1) PROPOSED EQUIPMENT CABINET • INSTALL (1) PROPOSED POWER CONDUIT • INSTALL (1) PROPOSED TELCO CONDUIT • INSTALL (1) PROPOSED NEMA 3 TELCO-FIBER BOX • INSTALL (1) PROPOSED GPS UNIT • INSTALL (3) PROPOSED RE-FRIENDLY FRP SCREEN ANTENNA ENCLOSURE • INSTALL (1) PROPOSED GEN PLUG INTERSECT CAMLOCK AT GROUND LEVEL • INSTALL (1) PROPOSED 12" WIDE ICE BRIDGE
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Current Status
- Issued on 12/16/2022
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2022 | VIVIAN LAO |
| Corrections Issued | 8/3/2022 | VIVIAN LAO |
| Plan Check Approved | 12/7/2022 | VIVIAN LAO |
| Issued | 12/16/2022 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/11/2022 | DANIEL CORONADO |
| Plan Approval | Cleared | 10/7/2022 | SANTOS SANCHEZ |
| Specific Plan | Cleared | 11/2/2022 | DARBY WHIPPLE |
Contact Information
| Engineer | Persellin,, Esra; Lic. No.: C88844 | 885 ORION WAY SAN MARCOS, CA 92078 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 8/2/2023 | Conditional Approval | RAFAEL CORTES |
| Deputy Reinf. Concrete | 8/3/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Wood Frame | 6/12/2025 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 7/31/2025 | Partial Inspection | RAFAEL CORTES |