12240 W VENICE BLVD 90066
Certificate Information: 12240 W VENICE BLVD 90066
- Application / Permit
- 22016-10000-20707
- Plan Check / Job No.
- B22LA13650
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePlan SECTOR SCOPE OF WORK: • INSTALL (6) PROPOSED PANEL ANTENNAS (2 PER SECTOR) • INSTALL (3) PROPOSED ANTENNA MOUNTS • INSTALL PROPOSED JUMPERS • INSTALL (12) PROPOSED RRHs (4 PER SECTOR) • INSTALL (3) PROPOSED OVER VOLTAGE PROTECTION DEVICE (OVP) (1 PER SECTOR) • INSTALL (3) PROPOSED HYBRID CABLES • INSTALL PROPOSED CABLE TRAYS ROOFTOP SCOPE OF WORK: • INSTALL (1) PROPOSED METAL PLATFORM WITH H-FRAME • INSTALL (1) PROPOSED CABLE TRAY • INSTALL (1) PROPOSED BBU IN CABINET • INSTALL (1) PROPOSED EQUIPMENT CABINET • INSTALL (1) PROPOSED POWER CONDUIT • INSTALL (1) PROPOSED TELCO CONDUIT • INSTALL (1) PROPOSED NEMA 3 TELCO-FIBER BOX • INSTALL (1) NON-BALLASTED ROOFTOP MOUNT • INSTALL (1) ANTENNA STAND-OFF WALL MOUNT • INSTALL (3) PROPOSED RE-FRIENDLY FRP SCREEN ANTENNA ENCLOSURE • INSTALL (1) PROPOSED GEN PLUG INTERSECT CAMLOCK AT GROUND LEVEL
- Permit Issued
- Issued on 11/11/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/7/2024
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2022 | VIVIAN LAO |
| Corrections Issued | 8/3/2022 | VIVIAN LAO |
| Plan Check Approved | 10/19/2022 | VIVIAN LAO |
| Issued | 11/11/2022 | APPLICANT |
| Permit Finaled | 6/7/2024 | FARHAD DADBIN |
Permit Application Clearance Information
| Plan Approval | Cleared | 10/7/2022 | SANTOS SANCHEZ |
| ZA Case | Cleared | 10/7/2022 | SANTOS SANCHEZ |
Contact Information
| Contractor | Motive Energy Telecommunications Group Inc; Lic. No.: 1021440-B | , |
| Engineer | Persellin,, Esra; Lic. No.: C88844 | 885 ORION WAY SAN MARCOS, CA 92078 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 11/9/2023 | Corrections Issued | FARHAD DADBIN |
| Wood Frame | 4/11/2024 | Approved | PAUL DAVIDSON |
| Final | 6/7/2024 | Permit Finaled | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV No Gas | FARHAD DADBIN |
| Smoke Detectors | 6/7/2024 | Approved | FARHAD DADBIN |