6006 S KANSAS AVE 90044
Certificate Information: 6006 S KANSAS AVE 90044
- Application / Permit
- 22016-10000-20659
- Plan Check / Job No.
- B22LA13598
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED CONVERT (E) GARAGE TO NEW A.D.U 426 SQ. FT PER ORDINANCE AND LAMC 12.22 A33(c)&(d).
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2022 | ZAW HAN |
| Corrections Issued | 7/19/2022 | ZAW HAN |
| Building Plans Picked Up | 7/25/2022 | APPLICANT |
| Plan Check Approved | 11/1/2022 | SHANGQIN XIE |
| Issued | 11/10/2022 | APPLICANT |
| CofO in Progress | 5/15/2024 | CRAIG DAVIS |
| Permit Finaled | 6/4/2024 | DEROLD HAUFF |
| CofO Issued | 6/4/2024 | DEROLD HAUFF |
| Permit Finaled | 6/4/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 8/4/2022 | WALLIE JONG |
| Sewer availability | Cleared | 8/8/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 10/25/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Inspection | RONNIE MINDANAO |
| Green Building Rough | 10/3/2023 | Corrections Issued | RONNIE MINDANAO |
| Wall Anchors | 10/3/2023 | Partial Inspection | RONNIE MINDANAO |
| Wood Frame | 10/3/2023 | Partial Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/6/2023 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/12/2023 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Approved | CRAIG DAVIS |
| Green Building Rough | 10/26/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Wall Anchors | 10/26/2023 | Approved | CRAIG DAVIS |
| Wood Frame | 10/26/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Interior/Exterior Lathing | 10/31/2023 | Approved | CRAIG DAVIS |
| Insulation | 11/3/2023 | Approved | CRAIG DAVIS |
| Drywall Nailing | 11/6/2023 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 11/21/2023 | Approved | JOSH MEISTER |
| Final | 3/20/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 3/20/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 3/20/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 3/20/2024 | Approved | CRAIG DAVIS |
| Wood Frame | 3/20/2024 | Approved | CRAIG DAVIS |
| Final | 4/24/2024 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 4/24/2024 | Partial Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Final | 4/29/2024 | Partial Inspection | CRAIG DAVIS |
| Green Building Final | 4/29/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 4/29/2024 | SGSOV Approved | CRAIG DAVIS |
| Final | 5/14/2024 | OK to Issue CofO | CRAIG DAVIS |