1115-1117 W 67TH ST 90044
Certificate Information: 1115-1117 W 67TH ST 90044
- Application / Permit
- 22016-10000-20647
- Plan Check / Job No.
- B22LA13581
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF (E) ATTACHED GARAGE TO ADU ( 294 SF) AND COVER PATIO (126 SF) PER STATE LAW AND GCS65852.2(e)(1)(A).
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2022 | ZAW HAN |
| Corrections Issued | 7/19/2022 | ZAW HAN |
| Building Plans Picked Up | 7/21/2022 | APPLICANT |
| Plan Check Approved | 9/19/2022 | FARSHAD ALIMOHAMADI |
| Issued | 9/19/2022 | APPLICANT |
| CofO in Progress | 8/23/2023 | ENRIQUE MIRELES |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2022 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 9/14/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/4/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/4/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/18/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/4/2023 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 4/4/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/4/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 4/4/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/27/2023 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/27/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/3/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 5/11/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 5/18/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/18/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 5/18/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/13/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/20/2023 | Approved | ENRIQUE MIRELES |
| Final | 8/10/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 8/10/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/10/2023 | Approved | ENRIQUE MIRELES |
| Final | 8/22/2023 | OK to Issue CofO | ENRIQUE MIRELES |