3401 W 8TH ST 90005
Certificate Information: 3401 W 8TH ST 90005
- Application / Permit
- 22016-10000-20583
- Plan Check / Job No.
- B22LA13532
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT FOR STORE, CHANGE OF USE FROM AUTOMOBILE SERVICE STATION TO RETAIL
- Permit Issued
- Issued on 10/26/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | TSE MING HUANG |
| Corrections Issued | 7/25/2022 | TSE MING HUANG |
| Quality Review Completed | 7/29/2022 | KEN GILL |
| Disabled Access Plans Picked Up | 8/10/2022 | APPLICANT |
| Applicant returned to address corrections | 8/16/2022 | TSE MING HUANG |
| Plan Check Approved | 9/6/2022 | TSE MING HUANG |
| Issued | 10/26/2022 | APPLICANT |
| CofO in Progress | 6/9/2023 | ALAN MORELOS |
| CofO Issued | 6/12/2023 | WINSTON DUNNING |
| Permit Finaled | 6/12/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/5/2022 | STEVE MELGAR |
| Redevelopment Project Area | Cleared | 8/9/2022 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2022 | STEVE MELGAR |
| DAS Clearance | Cleared | 8/23/2022 | TSE MING HUANG |
Contact Information
| Architect | Linane,, Donald Dean; Lic. No.: C18772 | 3500 W. BURBANK BLVD BURBANK, CA 91502 |
| Contractor | Sheene Paul Corporation; Lic. No.: 1015399-B | 940 S WESTERN AVE #B LOS ANGELES, CA 90006 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2022 | Corrections Issued | DARRYL ARNOLD |
| Insulation | 11/29/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Light Gage Steel Frame | 11/29/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Insulation | 11/30/2022 | Partial Inspection | ALAN MORELOS |
| Light Gage Steel Frame | 11/30/2022 | Approved | ALAN MORELOS |
| T-Bar Ceiling | 12/2/2022 | Corrections Issued | ALAN MORELOS |
| Insulation | 12/12/2022 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 12/12/2022 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 12/15/2022 | No Access for Inspection | RAMAZANALI ALMASI |
| Insulation | 12/21/2022 | Partial Inspection | GREGORY POMISH |
| T-Bar Ceiling | 12/21/2022 | Not Ready for Inspection | GREGORY POMISH |
| T-Bar Ceiling | 12/22/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 12/23/2022 | Not Ready for Inspection | ALFREDO LOPEZ |
| T-Bar Ceiling | 12/23/2022 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 12/27/2022 | Partial Approval | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 12/28/2022 | Approved | MARTIN TAVITIAN |
| Final | 3/18/2023 | Conditional Approval | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 3/18/2023 | SGSOV Approved | ALAN MORELOS |
| Smoke Detectors | 3/18/2023 | Approved | ALAN MORELOS |
| Wood Frame | 3/18/2023 | Approved | ALAN MORELOS |
| Final | 6/5/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/9/2023 | OK to Issue CofO | ALAN MORELOS |