4459 W DON TOMASO DR 90008

Certificate Information: 4459 W DON TOMASO DR 90008

Application / Permit
22016-10000-20506
Plan Check / Job No.
B22LA13477
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN: Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (1) SPECIAL CANTILEVERED COLUMN W/ GRADE BEAM.
Permit Issued
Issued on 10/24/2022
Issuing Office
Current Status
CofC Issued on 8/31/2023

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 HANS SANTIAGO
Corrections Issued 7/18/2022 HANS SANTIAGO
Quality Review Completed 7/18/2022 LIPING TENG
Applicant returned to address corrections 7/22/2022 HANS SANTIAGO
Applicant returned to address corrections 8/19/2022 HANS SANTIAGO
Plan Check Approved 9/6/2022 ANDREW SANTIAGO
Issued 10/24/2022 APPLICANT
OK for CofC 2/2/2023 DARRYL ARNOLD
CofC Issued 8/31/2023 WINSTON DUNNING

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/17/2022 JEANETTE VONG
Tenant Habitability Plan Cleared 9/14/2022 RICARDO BOHORQUEZ

Contact Information

Contractor Intrepid Builders Inc; Lic. No.: 1063638-B       ,
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 8232 GARVEY AVE 203      ROSEMEAD, CA 91770

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2022 Corrections Issued DARRYL ARNOLD
Deputy Drilled-In Anchors 11/7/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 11/7/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 11/7/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 11/9/2022 Approved DARRYL ARNOLD
Wood Frame 11/9/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 11/17/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 11/29/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 12/1/2022 Approved DARRYL ARNOLD
Final 1/18/2023 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 1/18/2023 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 1/18/2023 Not Ready for Inspection DARRYL ARNOLD
Final 2/2/2023 OK for CofC DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 2/2/2023 Approved DARRYL ARNOLD