21143 S BRIGHTON AVE 90501

Certificate Information: 21143 S BRIGHTON AVE 90501

Application / Permit
22016-10000-20464
Plan Check / Job No.
B22LA13420
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan convert detached garage into ADU
Permit Issued
Issued on 8/16/2022
Issuing Office
Current Status
CofO Issued on 3/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2022 APPLICANT
Assigned to Plan Check Engineer 7/18/2022 SUNMIN LEE
Corrections Issued 7/19/2022 SUNMIN LEE
Applicant returned to address corrections 8/4/2022 SUNMIN LEE
Applicant returned to address corrections 8/10/2022 SUNMIN LEE
Applicant returned to address corrections 8/12/2022 SUNMIN LEE
Plan Check Approved 8/16/2022 SUNMIN LEE
Issued 8/16/2022 APPLICANT
CofO in Progress 1/5/2023 EUGENE CASSIDY
Permit Finaled 3/9/2023 DANIEL ORRANTE
CofO Issued 3/9/2023 DANIEL ORRANTE
Permit Finaled 3/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/22/2022 JOSE HERNANDEZ
Roof/Waste drainage to street Cleared 7/22/2022 JOSE HERNANDEZ
Sewer availability Cleared 7/22/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 7/26/2022 JOSE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/1/2022 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 9/6/2022 Approved EUGENE CASSIDY
Footing/Foundation/Slab 9/6/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 9/20/2022 Corrections Issued EUGENE CASSIDY
HVAC-Rough 9/20/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 9/20/2022 Approved EUGENE CASSIDY
Wood Frame 9/20/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 9/26/2022 Approved EUGENE CASSIDY
HVAC-Rough 9/26/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 9/26/2022 Approved EUGENE CASSIDY
Sewer 9/26/2022 Approved EUGENE CASSIDY
Wood Frame 9/26/2022 Partial Approval EUGENE CASSIDY
Insulation 9/28/2022 Conditional Approval EUGENE CASSIDY
Interior/Exterior Lathing 9/28/2022 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/5/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Approved EUGENE CASSIDY
Drywall Nailing 10/12/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 12/2/2022 Corrections Issued JOHN KLARIN
Final 12/2/2022 Corrections Issued JOHN KLARIN
HVAC-Final 12/2/2022 Corrections Issued JOHN KLARIN
PLUMBING-Final 12/2/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 12/2/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 12/2/2022 Approved JOHN KLARIN
ELECTRICAL-Final 12/13/2022 Approved EUGENE CASSIDY
Final 12/13/2022 Corrections Issued EUGENE CASSIDY
HVAC-Final 12/13/2022 Approved EUGENE CASSIDY
Service/Power Release 12/13/2022 Not Ready for Inspection EUGENE CASSIDY
Final 1/4/2023 OK to Issue CofO EUGENE CASSIDY