1526 N EDGEMONT ST 90027

Certificate Information: 1526 N EDGEMONT ST 90027

Application / Permit
22016-10000-20402
Plan Check / Job No.
B22LA13371
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
TENANT IMPROVEMENT TO (E) MEDICAL OFFICE, INSTALL TWO (2) NEW IMAGING EQUIPMENT ON THE 5TH FLOOR OF MEDICAL OFFICE BUILDING AND REMOVE THE TWO (2) EXISTING SIEMENS GAMMA CAMERA IMAGING EQUIPMENT AND REMODELING OF THE ADJACENT PATIENT DRESSING AREA, TOILET ROOMS, STORAGE SUPPLY ROOM AND HOLDING AREA.
Permit Issued
Issued on 11/10/2022
Issuing Office
Current Status
Permit Finaled on 11/16/2023

Permit Application Status History

Submitted 7/12/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 SAM CHANG
Corrections Issued 7/26/2022 ARMEN JIVALAGIAN
Quality Review Completed 7/29/2022 PETER KIM
Plan Check Approved 9/15/2022 SAM CHANG
No Progress 10/6/2022 SAM CHANG
Plan Check Approved 10/6/2022 SAM CHANG
Issued 11/10/2022 APPLICANT
Permit Finaled 11/15/2023 RONALD JIMENEZ

Permit Application Clearance Information

DAS Clearance Cleared 9/15/2022 ARMEN JIVALAGIAN

Contact Information

Architect , ; Lic. No.: C34829       ,
Contractor Kaiser Foundation Health Plan Inc; Lic. No.: 370871-B 4175 E LA PALMA AVE STE 200      ANAHEIM, CA 92807
Engineer Tran,, Alfred; Lic. No.: S6429 2401 E KATELLA AVE STE #280      LOS ANGELES, CA 92806

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 12/15/2022 Partial Inspection JONATHAN QUACH
Insulation 1/10/2023 Not Ready for Inspection TIMOTHY POWELL
Light Gage Steel Frame 1/10/2023 Corrections Issued TIMOTHY POWELL
Insulation 1/13/2023 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 1/13/2023 Partial Approval RONALD JIMENEZ
Drywall Nailing 1/19/2023 Partial Approval VAHE KELEDJIAN
Drywall Nailing 2/3/2023 Partial Approval TIMOTHY POWELL
T-Bar Ceiling 3/16/2023 Partial Approval RONALD JIMENEZ
Drywall Nailing 3/20/2023 Partial Approval VAHE KELEDJIAN
Deputy Drilled-In Anchors 3/30/2023 Conditional Approval RONALD JIMENEZ
Structural Steel Frame 4/12/2023 Partial Approval RONALD JIMENEZ
Final 5/2/2023 Partial Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 5/2/2023 Partial Inspection TIMOTHY POWELL
Light Gage Steel Frame 7/12/2023 Partial Inspection TIMOTHY POWELL
Insulation 7/28/2023 Partial Approval VAHE KELEDJIAN
Drywall Nailing 8/23/2023 Partial Approval TIMOTHY POWELL
Final 11/15/2023 Permit Finaled RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 11/15/2023 Approved RONALD JIMENEZ