1526 N EDGEMONT ST 90027
Certificate Information: 1526 N EDGEMONT ST 90027
- Application / Permit
- 22016-10000-20402
- Plan Check / Job No.
- B22LA13371
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- TENANT IMPROVEMENT TO (E) MEDICAL OFFICE, INSTALL TWO (2) NEW IMAGING EQUIPMENT ON THE 5TH FLOOR OF MEDICAL OFFICE BUILDING AND REMOVE THE TWO (2) EXISTING SIEMENS GAMMA CAMERA IMAGING EQUIPMENT AND REMODELING OF THE ADJACENT PATIENT DRESSING AREA, TOILET ROOMS, STORAGE SUPPLY ROOM AND HOLDING AREA.
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/16/2023
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | SAM CHANG |
| Corrections Issued | 7/26/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 7/29/2022 | PETER KIM |
| Plan Check Approved | 9/15/2022 | SAM CHANG |
| No Progress | 10/6/2022 | SAM CHANG |
| Plan Check Approved | 10/6/2022 | SAM CHANG |
| Issued | 11/10/2022 | APPLICANT |
| Permit Finaled | 11/15/2023 | RONALD JIMENEZ |
Permit Application Clearance Information
| DAS Clearance | Cleared | 9/15/2022 | ARMEN JIVALAGIAN |
Contact Information
| Architect | , ; Lic. No.: C34829 | , |
| Contractor | Kaiser Foundation Health Plan Inc; Lic. No.: 370871-B | 4175 E LA PALMA AVE STE 200 ANAHEIM, CA 92807 |
| Engineer | Tran,, Alfred; Lic. No.: S6429 | 2401 E KATELLA AVE STE #280 LOS ANGELES, CA 92806 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/15/2022 | Partial Inspection | JONATHAN QUACH |
| Insulation | 1/10/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 1/10/2023 | Corrections Issued | TIMOTHY POWELL |
| Insulation | 1/13/2023 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/13/2023 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 1/19/2023 | Partial Approval | VAHE KELEDJIAN |
| Drywall Nailing | 2/3/2023 | Partial Approval | TIMOTHY POWELL |
| T-Bar Ceiling | 3/16/2023 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 3/20/2023 | Partial Approval | VAHE KELEDJIAN |
| Deputy Drilled-In Anchors | 3/30/2023 | Conditional Approval | RONALD JIMENEZ |
| Structural Steel Frame | 4/12/2023 | Partial Approval | RONALD JIMENEZ |
| Final | 5/2/2023 | Partial Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 5/2/2023 | Partial Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 7/12/2023 | Partial Inspection | TIMOTHY POWELL |
| Insulation | 7/28/2023 | Partial Approval | VAHE KELEDJIAN |
| Drywall Nailing | 8/23/2023 | Partial Approval | TIMOTHY POWELL |
| Final | 11/15/2023 | Permit Finaled | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 11/15/2023 | Approved | RONALD JIMENEZ |