5205 1/2 E LINCOLN AVE 90042
Certificate Information: 5205 1/2 E LINCOLN AVE 90042
- Application / Permit
- 22016-10000-20095
- Plan Check / Job No.
- B22LA13121
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO ADU LAMC 12.22 A.33(c)-(d))
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2022 | AUNG SOE |
| Corrections Issued | 7/6/2022 | AUNG SOE |
| Applicant returned to address corrections | 7/18/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 7/25/2022 | RAHEL BEYENE |
| Plan Check Approved | 7/27/2022 | FERNANDO FLORES |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 1/11/2023 | CRAIG VAUGHAN |
| Permit Finaled | 1/18/2023 | DEROLD HAUFF |
| CofO Issued | 1/18/2023 | DEROLD HAUFF |
| Permit Finaled | 1/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2022 | WALLIE JONG |
| Sewer availability | Cleared | 7/11/2022 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 7/14/2022 | MICHAEL SOTO |
| "Q" conditions | Cleared | 7/18/2022 | JASON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: C93049 | 7812 VASSAR AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2022 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/13/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/13/2022 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 9/13/2022 | Corrections Issued | SCOTT FINNILA |
| Insulation | 10/4/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 10/4/2022 | Corrections Issued | CRAIG VAUGHAN |
| Wood Frame | 10/4/2022 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 10/6/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 10/12/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 10/12/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/18/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 10/18/2022 | Approved | CRAIG VAUGHAN |
| Gas Test | 10/18/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 10/18/2022 | Approved | CRAIG VAUGHAN |
| Final | 12/7/2022 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 12/7/2022 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| Final | 1/4/2023 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 1/4/2023 | Approved | CRAIG VAUGHAN |
| Final | 1/10/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| Service/Power Release | 1/10/2023 | Approved | CRAIG VAUGHAN |