3715 S HILLCREST DR 90016
Certificate Information: 3715 S HILLCREST DR 90016
- Application / Permit
- 22016-10000-19929
- Plan Check / Job No.
- B22LA13028
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2022 | JOSEPH RAFOLS |
| Corrections Issued | 7/5/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 9/19/2022 | FERNANDO FLORES |
| Issued | 9/19/2022 | APPLICANT |
| CofO in Progress | 8/1/2023 | ANTHONY EGSON |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
| CofO Issued | 8/6/2023 | DEROLD HAUFF |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/31/2022 | TINA MIRANDA |
| Sewer availability | Cleared | 9/13/2022 | CINDY QI |
| Address approval | Cleared | 9/14/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/20/2023 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 1/20/2023 | Approved | ANTHONY EGSON |
| Sewer | 2/6/2023 | Approved | STUART CHAPMAN |
| Underground Mechanical | 2/6/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/7/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 3/7/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 3/7/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/14/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 3/14/2023 | Approved | ANTHONY EGSON |
| Insulation | 3/17/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 4/3/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/6/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 7/6/2023 | Approved | ANTHONY EGSON |
| Final | 7/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 7/6/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 7/6/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 7/6/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 7/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 7/6/2023 | Approved | ANTHONY EGSON |
| Final | 8/1/2023 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 8/1/2023 | Approved | ANTHONY EGSON |