4052 N SOMERS AVE 90065

Certificate Information: 4052 N SOMERS AVE 90065

Application / Permit
22016-10000-19879
Plan Check / Job No.
B22LA12977
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR REMODEL: 3 BEDROOM, TWO BATHROOMS LAUNDRY ROOM AND KITCHEN . -EXISTING PORCH TO BE ENCLOSED -223 SF ADDITION
Permit Issued
Issued on 1/16/2024
Issuing Office
Current Status
Issued on 1/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/27/2022 APPLICANT
Assigned to Plan Check Engineer 8/2/2022 SUNMIN LEE
Corrections Issued 8/3/2022 SUNMIN LEE
Applicant returned to address corrections 8/8/2023 JOSEPH RAFOLS
Plan Check Approved 10/23/2023 JOSEPH RAFOLS
Issued 1/16/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/26/2022 WALLIE JONG
Sewer availability Cleared 8/26/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/1/2022 WALLIE JONG
Grading Pre-Inspection Cleared 3/6/2023 KIRK LINKLATER
ZI Cleared 10/19/2023 ANDREA MAGANA-WITHERS

Contact Information

Contractor Owner-Builder       ,
Engineer Sin,, John Paul; Lic. No.: C91162 122 N GRAMERCY PL      LOS ANGELES, CA 90004

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 3/28/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/18/2024 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 4/30/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/29/2024 Not Ready for Inspection ROY SPAULDING
Green Building Rough 10/29/2024 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 12/2/2024 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 12/13/2024 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 1/30/2025 Approved THOMAS LOGRASSO
PLUMBING-Rough 1/30/2025 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 3/21/2025 Approved NICHOLAS LOPEZ
Green Building Rough 3/21/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 3/21/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 3/21/2025 Partial Approval NICHOLAS LOPEZ
Insulation 4/11/2025 Partial Approval NICHOLAS LOPEZ
Drywall Nailing 4/22/2025 Approved NICHOLAS LOPEZ
Insulation 4/22/2025 Approved NICHOLAS LOPEZ
Service/Power Release 4/22/2025 Approved NICHOLAS LOPEZ
Final 9/5/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 9/5/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 9/5/2025 Approved NICHOLAS LOPEZ