10367 W CHEVIOT DR 90064
Certificate Information: 10367 W CHEVIOT DR 90064
- Application / Permit
- 22016-10000-19877
- Plan Check / Job No.
- B22LA12976
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Proposed interior remodel to existing SFD, to convert (e) hallway into an outdoor covered porch with new deck on top, new sliding door.
- Permit Issued
- Issued on 10/17/2022
- Issuing Office
- Current Status
- Permit Finaled on 5/17/2023
Permit Application Status History
| Submitted | 7/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2022 | MICHAEL LOPEZ |
| Corrections Issued | 7/11/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 8/16/2022 | MICHAEL LOPEZ |
| Issued | 10/17/2022 | APPLICANT |
| Permit Finaled | 5/16/2023 | CLAYTON GRAHAM |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/13/2022 | CONNIE CHAUV |
| Roof/Waste drainage to street | Cleared | 7/14/2022 | DINAH GARIN |
| ZA Case | Cleared | 7/14/2022 | MAXFIELD VERMY |
| ZA Case | Cleared | 7/14/2022 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 8/4/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mixter,, Thomas J; Lic. No.: C51041 | 2345 COUNTY RD 630 DEL RIO, TX 78840 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/1/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 12/7/2022 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 12/22/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 12/28/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 3/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Wood Construction | 3/6/2023 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Wood Construction | 3/8/2023 | Conditional Approval | DAVID FEILER |
| Insulation | 3/21/2023 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/21/2023 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 3/24/2023 | Approved | ASHLEY THOMPSON |
| Final | 5/16/2023 | Permit Finaled | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Smoke Detectors | 5/16/2023 | Approved | CLAYTON GRAHAM |