5653 1/2 W CLEMSON ST 8 90016
Certificate Information: 5653 1/2 W CLEMSON ST 8 90016
- Application / Permit
- 22016-10000-19865
- Plan Check / Job No.
- B22LA12970
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert portion of existing garage to ADU.
- Permit Issued
- Issued on 9/13/2022
- Issuing Office
- Current Status
- CofO Issued on 1/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/11/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 8/24/2022 | FARSHAD ALIMOHAMADI |
| Issued | 9/13/2022 | APPLICANT |
| CofO in Progress | 12/1/2023 | JOSE AVILA |
| No Progress | 12/26/2023 | SCOTT FINNILA |
| CofO in Progress | 1/2/2024 | SCOTT FINNILA |
| Permit Finaled | 1/7/2024 | DEROLD HAUFF |
| CofO Issued | 1/7/2024 | DEROLD HAUFF |
| Permit Finaled | 1/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/8/2022 | MICHAEL SOTO |
| Address approval | Cleared | 8/10/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 8/10/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | TREVOR QUAN |
Contact Information
| Architect | , ; Lic. No.: C34210 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/12/2022 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 10/18/2022 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 11/4/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 12/6/2022 | Approved | JOSE AVILA |
| Wood Frame | 1/12/2023 | Corrections Issued | JOSE AVILA |
| Wood Frame | 1/18/2023 | Partial Approval | JOSE AVILA |
| Insulation | 1/23/2023 | Partial Approval | JOSE AVILA |
| Special/Order Compliance | 8/18/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 9/1/2023 | Approved | JOSE AVILA |
| Final | 10/12/2023 | Corrections Issued | JOSE AVILA |
| Final | 11/2/2023 | Corrections Issued | JOSE AVILA |
| Final | 11/29/2023 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 11/29/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 11/29/2023 | Approved | JOSE AVILA |