217 S CHURCH LANE 90049

Certificate Information: 217 S CHURCH LANE 90049

Application / Permit
22016-10000-19863
Plan Check / Job No.
B22LA12968
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePlan Convert existing 22 x 52 attached garage to ADU
Permit Issued
Issued on 3/28/2023
Issuing Office
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 CRYSTEL MAALOUF
Corrections Issued 8/10/2022 CRYSTEL MAALOUF
Quality Review Completed 8/10/2022 GARO TELMI
Applicant returned to address corrections 11/21/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 12/23/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 1/10/2023 CRYSTEL MAALOUF
Plan Check Approved 1/31/2023 CRYSTEL MAALOUF
Issued 3/28/2023 APPLICANT
CofO in Progress 7/19/2024 CASIMIR BRITTON
Permit Finaled 7/24/2024 DAVID TSAU
CofO Issued 7/24/2024 DAVID TSAU
Permit Finaled 7/24/2024 DAVID TSAU

Permit Application Clearance Information

"Q" conditions Cleared 8/26/2022 STEVEN WECHSLER
Sewer availability Cleared 8/30/2022 JENSON LEE
Specific Plan Cleared 10/13/2022 ROBERT SANCHEZ
Specific Plan Cleared 10/19/2022 KEVIN FULTON
Specific Plan Cleared 10/19/2022 KEVIN FULTON
Address approval Cleared 10/20/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 10/20/2022 JENSON LEE
Roof/Waste drainage to street Cleared 10/20/2022 JENSON LEE
Grading Pre-Inspection Cleared 11/7/2022 KIRK LINKLATER

Contact Information

Contractor United Construction Group Inc; Lic. No.: 1077065-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/10/2023 Approved SORIN CIRSTOIU
Pre-Inspection 4/11/2023 Not Ready for Inspection SORIN CIRSTOIU
Deputy Drilled-In Anchors 5/9/2023 Conditional Approval SORIN CIRSTOIU
Footing/Foundation/Slab 5/10/2023 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Not Ready for Inspection ALAN NOVAK
Wood Frame 6/21/2023 Not Ready for Inspection ALAN NOVAK
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval ALAN NOVAK
Interior/Exterior Lathing 9/19/2023 Approved ALAN NOVAK
Wood Frame 9/25/2023 Conditional Approval ALAN NOVAK
Insulation 10/2/2023 Approved ALAN NOVAK
Insulation 10/5/2023 Approved ALAN NOVAK
Drywall Nailing 10/10/2023 Approved ALAN NOVAK
Pre-Inspection 10/12/2023 Approved ALAN NOVAK
Drywall Nailing 10/20/2023 Approved ALAN NOVAK
Pre-Inspection 10/27/2023 Approved ALAN NOVAK
Interior/Exterior Lathing 11/9/2023 Approved ALAN NOVAK
Pre-Inspection 11/16/2023 Approved ALAN NOVAK
Final 11/21/2023 Not Ready for Inspection ALAN NOVAK
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Approved ALAN NOVAK
Smoke Detectors 11/21/2023 Approved ALAN NOVAK
Wood Frame 11/21/2023 Approved ALAN NOVAK
Pre-Inspection 11/28/2023 Approved ALAN NOVAK
Interior/Exterior Lathing 12/8/2023 Approved ALAN NOVAK
Special/Order Compliance 12/22/2023 Approved ALAN NOVAK
Final 1/17/2024 Corrections Issued CASIMIR BRITTON
Final 2/2/2024 Not Ready for Inspection CASIMIR BRITTON
Final 6/11/2024 Not Ready for Inspection CASIMIR BRITTON
Final 7/19/2024 OK to Issue CofO CASIMIR BRITTON