1833 W 43RD PL 90062
Certificate Information: 1833 W 43RD PL 90062
- Application / Permit
- 22016-10000-19856
- Plan Check / Job No.
- B22LA12963
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/11/2022
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2022 | DANIEL YIP |
| Corrections Issued | 7/7/2022 | DANIEL YIP |
| Applicant returned to address corrections | 7/14/2022 | DANIEL YIP |
| Plan Check Approved | 9/2/2022 | DANIEL YIP |
| Issued | 11/11/2022 | APPLICANT |
| CofO in Progress | 9/13/2023 | SABAS ALONSO |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
| CofO Issued | 9/21/2023 | DEROLD HAUFF |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 7/11/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | TREVOR QUAN |
| Construction near power lines | Cleared | 9/1/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Everlast Home Builders Inc; Lic. No.: 910398-B | 11054 VENTURA BLVD #321 STUDIO CITY, CA 91604 |
| Engineer | Orellana,, Fredy Orlando; Lic. No.: C68955 | 100 SPECTRUM CENTER DR STE 9-283 IRVINE, CA 92618 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/31/2023 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 1/31/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 1/31/2023 | Corrections Issued | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 2/2/2023 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 2/2/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/2/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/2/2023 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 2/2/2023 | Corrections Issued | JOSEPH MCGARRY |
| Underground Mechanical | 2/2/2023 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 2/22/2023 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/1/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/15/2023 | Corrections Issued | SABAS ALONSO |
| Insulation | 3/15/2023 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 3/15/2023 | Partial Approval | SABAS ALONSO |
| Insulation | 3/23/2023 | No Access for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 3/23/2023 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 4/5/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 4/5/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/5/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 4/5/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/14/2023 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 4/18/2023 | Partial Approval | SABAS ALONSO |
| Insulation | 5/3/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 5/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/11/2023 | Approved | CALEB MEISTER |
| Shower Pan | 5/11/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 5/24/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/30/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Final | 6/26/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 6/26/2023 | Approved | SABAS ALONSO |
| Final | 7/17/2023 | Corrections Issued | STUART CHAPMAN |
| Final | 9/12/2023 | OK to Issue CofO | SABAS ALONSO |