818 E 119TH ST 90059
Certificate Information: 818 E 119TH ST 90059
- Application / Permit
- 22016-10000-19855
- Plan Check / Job No.
- B22LA12962
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert existing 2-car detached garage to Accessory Dwelling Unit per CA Govt Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/11/2022
- Issuing Office
- Current Status
- CofO Issued on 9/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | HANS SANTIAGO |
| Corrections Issued | 7/14/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 8/22/2022 | HANS SANTIAGO |
| Plan Check Approved | 8/24/2022 | ANDREW SANTIAGO |
| Plan Check Approved | 9/6/2022 | ANDREW SANTIAGO |
| Issued | 9/11/2022 | APPLICANT |
| CofO in Progress | 9/20/2024 | BARRY HACHE |
| Permit Finaled | 9/24/2024 | ANSON MAGLASANG |
| CofO Issued | 9/24/2024 | ANSON MAGLASANG |
| Permit Finaled | 9/24/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 7/21/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 8/23/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/19/2022 | Approved | JOHN KLARIN |
| Pre-Inspection | 10/28/2022 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 6/21/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 6/27/2023 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 7/14/2023 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 7/28/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 7/28/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 8/3/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 8/3/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 8/8/2023 | Partial Approval | JOHN KLARIN |
| Underground Mechanical | 8/10/2023 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/4/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 10/4/2023 | Corrections Issued | JAMES CHAVEZ |
| MERV13>=Rough | 10/4/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 10/4/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 10/11/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 10/11/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/11/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/17/2023 | Corrections Issued | JOHN KLARIN |
| Wood Frame | 10/31/2023 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 11/3/2023 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/7/2023 | Approved | JOHN KLARIN |
| Insulation | 11/22/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/22/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 12/22/2023 | Corrections Issued | JOHN KLARIN |
| Drywall Nailing | 12/28/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 1/23/2024 | Partial Approval | JAMES CHAVEZ |
| Shower Pan | 1/23/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 3/13/2024 | Approved | BEN MOLSTAD |
| Pre-Inspection | 3/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 8/27/2024 | Corrections Issued | BARRY HACHE |
| MERV13>=Final | 8/27/2024 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 8/27/2024 | Approved | BARRY HACHE |
| Special/Order Compliance | 8/27/2024 | Partial Inspection | BEN MOLSTAD |
| Final | 9/5/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Final | 9/13/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Approved | BEN MOLSTAD |
| Final | 9/18/2024 | OK to Issue CofO | BARRY HACHE |