7407 S WESTLAWN AVE 90045
Certificate Information: 7407 S WESTLAWN AVE 90045
- Application / Permit
- 22016-10000-19840
- Plan Check / Job No.
- B22LA12930
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: INTERIOR REMODEL AND PORCH ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 9/13/2022
- Issuing Office
- Current Status
- CofO Issued on 3/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2022 | DANIEL YIP |
| Corrections Issued | 7/10/2022 | DANIEL YIP |
| Plan Check Approved | 8/23/2022 | DANIEL YIP |
| Issued | 9/13/2022 | APPLICANT |
| CofO in Progress | 3/5/2024 | BOBBY KEY |
| Permit Finaled | 3/11/2024 | DANIEL ORRANTE |
| CofO Issued | 3/11/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/11/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/4/2022 | NATHAN ROMINE |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 8/15/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 6/30/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 6/30/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 6/30/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 7/7/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 7/7/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 7/7/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 7/12/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 7/12/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 7/12/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 7/18/2023 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 7/18/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 7/20/2023 | Partial Approval | BOBBY KEY |
| Shower Pan | 7/20/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 7/24/2023 | Approved | BOBBY KEY |
| Green Building Rough | 7/24/2023 | Approved | BOBBY KEY |
| Insulation | 7/24/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 7/24/2023 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 7/28/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/16/2023 | Approved | JESUS PINEDA |
| Final | 11/16/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 11/16/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 11/16/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 11/16/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 11/16/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Not Ready | BOBBY KEY |
| Final | 2/28/2024 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Not Ready | BOBBY KEY |
| Final | 3/5/2024 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Approved | BOBBY KEY |