700 W 5TH ST 90071

Certificate Information: 700 W 5TH ST 90071

Application / Permit
22016-10000-19649
Plan Check / Job No.
B22LA12800
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
TENANT IMPROVEMENT OF RESTAURANT/KITCHEN AND BAR. REMODEL FROM (E) VACANT RESTAURANT SPACE & RESTROOMS. MAIN LEVEL 3088 SQ FT, MEZZANINE LEVEL 1050 SQ FT, MEZZANINE STORAGE 700 SQ FT, TOTAL RESTAURANT AREA 4838 SQ FT
Permit Issued
Issued on 5/5/2023
Issuing Office
Metro
Current Status
Permit Finaled on 12/24/2024

Permit Application Status History

Submitted 6/30/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 ARSALAN SHABESTARI
Disabled Access Plans Picked Up 7/22/2022 APPLICANT
Green Plans Picked Up 7/23/2022 APPLICANT
Corrections Issued 8/11/2022 ARSALAN SHABESTARI
Quality Review Completed 8/18/2022 KEN GILL
Building Plans Picked Up 8/22/2022 APPLICANT
Plan Check Approved 2/7/2023 ARSALAN SHABESTARI
Issued 5/5/2023 APPLICANT
Permit Finaled-Status Void 11/18/2024 JEROME BLACKWOOD
Re-Activate Permit 11/19/2024 JEROME BLACKWOOD
Permit Finaled 12/20/2024 PAUL BAZERKANIAN

Permit Application Clearance Information

Green Code Cleared 8/8/2022 MICHAEL AYERS
"D" conditions Cleared 9/15/2022 KENTON TRINH
ZA Case Cleared 9/15/2022 KENTON TRINH
ZA Case Cleared 9/16/2022 RICARDO MARTINEZ
ZA Case Cleared 9/16/2022 RICARDO MARTINEZ
Fire Marshal Fire Life Safety Cleared 12/19/2022 RONILO MULAWIN
Food Service Establishment Cleared 1/3/2023 PAWAN VERMA
DAS Clearance Cleared 1/12/2023 ARSALAN SHABESTARI
Food establishment approval Cleared 1/24/2023 LACDHS APPROVED

Contact Information

Contractor Phoenix Construction And Management Inc; Lic. No.: 815136-B 515 S FLOWER STREET, STE 1270      LOS ANGELES, CA 90071

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 11/2/2023 Conditional Approval RAMAZANALI ALMASI
Deputy Steel/Welding 11/3/2023 Conditional Approval KATY RAMIREZ
Pre-Inspection 12/8/2023 Partial Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 12/20/2023 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 1/8/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/2/2024 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 3/1/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 3/22/2024 Partial Approval LUIS CCAMACHO
Deputy Drilled-In Anchors 3/26/2024 No Access for Inspection MICHAEL ROSENBERG
Light Gage Steel Frame 4/19/2024 Partial Inspection JEROME BLACKWOOD
Drywall Nailing 4/29/2024 Partial Approval LUIS CCAMACHO
Insulation 5/1/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 5/2/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 5/16/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 6/3/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 8/8/2024 Partial Approval LUIS CCAMACHO
Insulation 8/21/2024 Partial Approval LUIS CCAMACHO
Final 10/31/2024 Not Ready for Inspection PAUL BAZERKANIAN
Green Building Final 10/31/2024 Not Ready for Inspection PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Not Ready PAUL BAZERKANIAN
Smoke Detectors 10/31/2024 Not Ready for Inspection PAUL BAZERKANIAN
Final 11/18/2024 Partial Inspection JEROME BLACKWOOD
Green Building Final 11/18/2024 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 11/18/2024 Approved JEROME BLACKWOOD
Final 12/20/2024 Permit Finaled PAUL BAZERKANIAN