7811 S CRENSHAW BLVD 90043

Certificate Information: 7811 S CRENSHAW BLVD 90043

Application / Permit
22016-10000-19580
Plan Check / Job No.
B22LA12741
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install New Ordinary Steel Moment Frame
Permit Issued
Issued on 1/20/2023
Issuing Office
Current Status
CofC Issued on 4/7/2023

Permit Application Status History

Submitted 6/30/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 JESSE VIDUYA
Corrections Issued 7/14/2022 JESSE VIDUYA
Quality Review Completed 7/22/2022 HANS SANTIAGO
Applicant returned to address corrections 9/20/2022 JESSE VIDUYA
Plan Check Approved 12/1/2022 JESSE VIDUYA
Issued 1/20/2023 APPLICANT
OK for CofC 4/6/2023 DARRYL ARNOLD
CofC Issued 4/7/2023 WINSTON DUNNING

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 9/6/2022 KYLE WINSTON
Historic Resource Verification Cleared 10/18/2022 MAX LODER
Redevelopment Project Area Cleared 11/15/2022 GRACIELA ACOSTA
Tenant Habitability Plan Cleared 12/21/2022 RICARDO BOHORQUEZ

Contact Information

Contractor American Retrofitters Corp; Lic. No.: 1020382-B       ,
Engineer Vartanian,, Albert; Lic. No.: C39989 PO BOX 857      VERDUGO CITY, CA 91046

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2023 Approved DARRYL ARNOLD
Deputy Steel/Welding 2/10/2023 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 2/15/2023 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 2/15/2023 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 2/16/2023 Approved DARRYL ARNOLD
Structural Steel Frame 2/16/2023 Approved DARRYL ARNOLD
Wood Frame 2/16/2023 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 2/22/2023 Conditional Approval DARRYL ARNOLD
Deputy Wood Construction 2/23/2023 Conditional Approval DARRYL ARNOLD
Deputy Wood Construction 2/24/2023 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 2/24/2023 Approved DARRYL ARNOLD
Interior/Exterior Lathing 3/14/2023 Approved DARRYL ARNOLD
Final 4/3/2023 Conditional Approval DARRYL ARNOLD
METHANE-Final 4/3/2023 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/3/2023 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 4/3/2023 Approved DARRYL ARNOLD
Special/Order Compliance 4/5/2023 Corrections Issued DARRYL ARNOLD
Final 4/6/2023 OK for CofC DARRYL ARNOLD