3620 S 7TH AVE 90018

Certificate Information: 3620 S 7TH AVE 90018

Application / Permit
22016-10000-19535
Plan Check / Job No.
B22LA12710
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING GARAGE TO BE CONVERTED TO ADU COMPLY WITH DEPARTMENT ORDER effective date 02/17/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 9/22/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2022 APPLICANT
Assigned to Plan Check Engineer 6/29/2022 JOSEPH RAFOLS
Corrections Issued 6/29/2022 JOSEPH RAFOLS
Plan Check Approved 9/22/2022 SHAHEN AKELYAN
Issued 9/22/2022 APPLICANT
CofO in Progress 5/11/2023 ROBERT MINASSIANS
Permit Finaled 6/28/2023 BRUCE TODD
CofO Issued 6/28/2023 BRUCE TODD
Permit Finaled 6/28/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 7/5/2022 TREVOR QUAN
Sewer availability Cleared 7/5/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 7/6/2022 TREVOR QUAN
HPOZ Cleared 9/1/2022 DANIEL MATA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/28/2022 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 9/28/2022 Partial Approval WILLIAM MICHALAK
Pre-Inspection 9/28/2022 Approved WILLIAM MICHALAK
Deputy Drilled-In Anchors 9/29/2022 Approved GLEN RAND
Footing/Foundation/Slab 9/30/2022 Corrections Issued GLEN RAND
PLUMBING-Rough 9/30/2022 Corrections Issued GLEN RAND
PLUMBING-Rough 10/13/2022 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 10/28/2022 Partial Approval WILLIAM MICHALAK
Gas Test 10/28/2022 Approved WILLIAM MICHALAK
PLUMBING-Rough 10/28/2022 Approved WILLIAM MICHALAK
Underground Mechanical 10/28/2022 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 11/9/2022 Corrections Issued GLEN RAND
PLUMBING-Rough 11/9/2022 Corrections Issued GLEN RAND
ELECTRICAL-Rough 11/22/2022 Approved GLEN RAND
Interior/Exterior Lathing 11/22/2022 Not Ready for Inspection GLEN RAND
PLUMBING-Rough 11/22/2022 Approved GLEN RAND
HVAC-Rough 11/28/2022 Approved GLEN RAND
Interior/Exterior Lathing 11/28/2022 Corrections Issued GLEN RAND
Wood Frame 11/28/2022 Corrections Issued GLEN RAND
Interior/Exterior Lathing 12/1/2022 Approved GLEN RAND
Insulation 12/5/2022 Approved GLEN RAND
BUILDING-Rough-Frame 12/7/2022 Approved GLEN RAND
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Approved GLEN RAND
Shower Pan 12/7/2022 Approved GLEN RAND
Drywall Nailing 12/13/2022 Approved GLEN RAND
Interior/Exterior Lathing 12/13/2022 Approved GLEN RAND
ELECTRICAL-Final 1/17/2023 Corrections Issued GLEN RAND
Final 1/17/2023 Corrections Issued GLEN RAND
HVAC-Final 1/17/2023 Approved GLEN RAND
PLUMBING-Final 1/17/2023 Corrections Issued GLEN RAND
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Approved GLEN RAND
Smoke Detectors 1/17/2023 Approved GLEN RAND
Special/Order Compliance 1/17/2023 Corrections Issued GLEN RAND
ELECTRICAL-Final 1/23/2023 Conditional Approval GLEN RAND
Final 1/23/2023 Corrections Issued GLEN RAND
PLUMBING-Final 1/23/2023 Approved GLEN RAND
Final 4/19/2023 Corrections Issued GLEN RAND
Final 5/8/2023 Corrections Issued GLEN RAND
Final 5/11/2023 OK to Issue CofO GLEN RAND